OCTARY USA Β· INTERCONNECTION QUEUESCompleted queue projects in ISO-NE (New England) (2010 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Manchester Street Station increase Gas |
492 MW | |
| Bingham Wind Onshore wind |
185 MW | |
| RISEP Increase Gas |
66.0 MW | |
| Groton Wind Farm Onshore wind |
48.0 MW | |
| Verso Androscoggin Energy Cogen 1, 2, & 3 Increase Gas |
26.0 MW | |
| Bucksport G5 Other |
25.0 MW | |
| Manchester Street Station Exciter Upgrades & incre Gas |
12.0 MW | |
| Georgia Mountain Community Wind Onshore wind |
10.0 MW | |
| Pisgah Mountain Onshore wind |
9.0 MW | |
| Burgess BioPower Increase Other |
9.0 MW | |
| Salem Harbor Station Increase Other |
8.0 MW | |
| Kendall #3 Back Pressure Steam Turbine Gas |
7.5 MW | |
| Mass Power Increase Gas |
5.0 MW | |
| Gulf Island Unit 2 Increase Hydro |
4.4 MW | |
| Spruce Mountain Wind Increase Onshore wind |
2.0 MW |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)39 Β· 2,837 MW
- PJM (Mid-Atlantic, Midwest)81 Β· 2,800 MW
- Southeast (non-ISO utilities)4 Β· 2,438 MW
- SPP (Southwest Power Pool)15 Β· 2,398 MW
- West (non-ISO utilities)55 Β· 1,898 MW
- ERCOT (Texas)9 Β· 1,687 MW
- ISO-NE (New England)15 Β· 909 MW
- MISO (Midcontinent)13 Β· 868 MW
- NYISO (New York)4 Β· 12.4 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)