United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in ISO-NE (New England) (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown15909 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn121,337 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Manchester Street Station increase
Gas
492 MWOperating Providence, RIISO-NE May 2010target 2010
Bingham Wind
Onshore wind
185 MWOperating Somerset, MEISO-NE May 2010target 2016
RISEP Increase
Gas
66.0 MWOperating Providence, RIISO-NE May 2010target 2012
Groton Wind Farm
Onshore wind
48.0 MWOperating Grafton, NHISO-NE Sep 2010target 2012
Verso Androscoggin Energy Cogen 1, 2, & 3 Increase
Gas
26.0 MWOperating Franklin, MEISO-NE May 2010target 2012
Bucksport G5
Other
25.0 MWOperating Hancock, MEISO-NE Oct 2010target 2012
Manchester Street Station Exciter Upgrades & incre
Gas
12.0 MWOperating Providence, RIISO-NE Jul 2010target 2011
Georgia Mountain Community Wind
Onshore wind
10.0 MWOperating Chittenden, VTISO-NE May 2010target 2012
Pisgah Mountain
Onshore wind
9.0 MWOperating Penobscot, MEISO-NE Oct 2010target 2016
Burgess BioPower Increase
Other
9.0 MWOperating Coos, NHISO-NE Oct 2010target 2014
Salem Harbor Station Increase
Other
8.0 MWOperating Essex, MAISO-NE Dec 2010
Kendall #3 Back Pressure Steam Turbine
Gas
7.5 MWOperating Middlesex, MAISO-NE May 2010target 2010
Mass Power Increase
Gas
5.0 MWOperating Hampden, MAISO-NE Sep 2010target 2011
Gulf Island Unit 2 Increase
Hydro
4.4 MWOperating Androscoggin, MEISO-NE Dec 2010target 2011
Spruce Mountain Wind Increase
Onshore wind
2.0 MWOperating Oxford, MEISO-NE Jan 2010target 2010

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)