Withdrawn queue requests in West (non-ISO utilities) — page 73

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 73 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 2008-G4
Onshore wind
30.0 MWWithdrawn / abandoned West Feb 2008target 2012
Onshore wind project 2013-G2
Onshore wind
30.0 MWWithdrawn / abandoned West Apr 2013target 2014
Solar project GI-2009-2, Alamosa County
Solar
30.0 MWWithdrawn / abandoned Alamosa, COWest Feb 2009target 2012
Other project 4, Elmore County
Other
30.0 MWWithdrawn / abandoned Elmore, IDWest Feb 2001target 2005
Battery storage project 384, Yellowstone County
Battery storage
30.0 MWWithdrawn / abandoned Yellowstone, MTWest Jun 2020target 2023
Solar project Q112, Maricopa County
Solar
30.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2010target 2012
Solar project PIS020, Sanpete County
Solar · PacifiCorp
30.0 MWWithdrawn / abandoned Sanpete, UTWest Jun 2022target 2026
Onshore wind project 2009-G3
Onshore wind
30.0 MWWithdrawn / abandoned West Apr 2009target 2015
Solar + storage project TCS-31, Uinta County
Solar + storage
30.0 MWWithdrawn / abandoned Uinta, WYWest Apr 2019target 2022
Solar project 1054, Millard County
Solar
30.0 MWWithdrawn / abandoned Millard, UTWest Jul 2018target 2020
Onshore wind project 860, Carbon County
Onshore wind
30.0 MWWithdrawn / abandoned Carbon, WYWest Apr 2017target 2019
Solar project 1039, Cache County
Solar
30.0 MWWithdrawn / abandoned Cache, UTWest Jun 2018target 2020
Solar project GI-2016-8, Alamosa County
Solar
30.0 MWWithdrawn / abandoned Alamosa, COWest Apr 2016target 2018
Solar project GI-2010-13, Pueblo County
Solar
30.0 MWWithdrawn / abandoned Pueblo, COWest Oct 2010target 2013
Battery storage project 383, Missoula County
Battery storage
30.0 MWWithdrawn / abandoned Missoula, MTWest Jun 2020target 2023
Solar project GI-2010-9, Pueblo County
Solar
30.0 MWWithdrawn / abandoned Pueblo, COWest Jun 2010target 2012
Solar project GI-2013-3, Pueblo County
Solar
30.0 MWWithdrawn / abandoned Pueblo, COWest Apr 2013target 2016
Onshore wind project GI-2003-4, Laramie County
Onshore wind
30.0 MWWithdrawn / abandoned Laramie, WYWest Nov 2003target 2004
Solar project Q524, Coconino County
Solar
30.0 MWWithdrawn / abandoned Coconino, AZWest Mar 2023target 2026
Solar project 2018-G3
Solar
30.0 MWWithdrawn / abandoned West Feb 2018target 2020
Solar project Q110, Maricopa County
Solar
30.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2010target 2012
Battery storage project 1127, Uinta County
Battery storage
30.0 MWWithdrawn / abandoned Uinta, WYWest Apr 2019target 2022
Gas project GI-0618, Crawford County
Gas
30.0 MWWithdrawn / abandoned Crawford, IAWest Dec 2006
Geothermal project G0437, Lake County
Geothermal
30.0 MWWithdrawn / abandoned Lake, ORWest Oct 2010target 2013
Solar project Company 130, Clark County
Solar
30.0 MWWithdrawn / abandoned Clark, NVWest Mar 2014target 2016
Solar project 776, Box Elder County
Solar
30.0 MWWithdrawn / abandoned Box Elder, UTWest Jul 2016target 2018
Solar + storage project Q398, Navajo County
Solar + storage
30.0 MWWithdrawn / abandoned Navajo, AZWest Sep 2021target 2025
Solar project GI-2010-12, Alamosa County
Solar
30.0 MWWithdrawn / abandoned Alamosa, COWest Aug 2010target 2013
Solar project 439, Elmore County
Solar
30.0 MWWithdrawn / abandoned Elmore, IDWest Oct 2014
Solar + storage project C3-057, Box Elder County
Solar + storage
30.0 MWWithdrawn / abandoned Box Elder, UTWest May 2023target 2025
Cal Geo
Geothermal · Cal Geo Company
30.0 MWWithdrawn / abandoned Modoc, CAWest Nov 2001target 2003
Solar project 314, Silver Bow County
Solar
30.0 MWWithdrawn / abandoned Silver Bow, MTWest Mar 2017target 2018
Solar project GI-2010-7, Alamosa County
Solar
30.0 MWWithdrawn / abandoned Alamosa, COWest Mar 2010target 2012
Onshore wind project GI-0121, Buffalo County
Onshore wind
30.0 MWWithdrawn / abandoned Buffalo, SDWest Dec 2001
Solar project 18-04191, Weld County
Solar
30.0 MWWithdrawn / abandoned Weld, COWest Apr 2018target 2018
Solar project GI-2016-30, Weld County
Solar
30.0 MWWithdrawn / abandoned Weld, COWest Nov 2016target 2019
USGeothermal
Geothermal · US Geothermal, Inc.
30.0 MWWithdrawn / abandoned Cassia, IDWest Mar 2004target 2006
Other project 192, Douglas County
Other
30.0 MWWithdrawn / abandoned Douglas, ORWest Jan 2008
Solar project Company 127, Clark County
Solar
30.0 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2016
Other project C3-017, Crook County
Other
30.0 MWWithdrawn / abandoned Crook, ORWest Apr 2023target 2025
Solar project 18-02091, Larimer County
Solar
30.0 MWWithdrawn / abandoned Larimer, COWest Feb 2018target 2018
Solar project TCS-25, Iron County
Solar
30.0 MWWithdrawn / abandoned Iron, UTWest Jan 2019target 2022
Solar project GI-2010-18, Pueblo County
Solar
30.0 MWWithdrawn / abandoned Pueblo, COWest Nov 2010target 2012
Onshore wind project 2008-G5
Onshore wind
30.0 MWWithdrawn / abandoned West Feb 2008target 2012
Onshore wind project 2013-G1
Onshore wind
30.0 MWWithdrawn / abandoned West Apr 2013target 2014
Battery storage project 385, Lewis And Clark County
Battery storage
30.0 MWWithdrawn / abandoned Lewis And Clark, MTWest Jun 2020target 2023
Solar project GI-2012-6, Arapahoe County
Solar
30.0 MWWithdrawn / abandoned Arapahoe, COWest Oct 2012target 2016
Solar project Q111, Maricopa County
Solar
30.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2010target 2012
Solar + storage project Q63, Kern County
Solar + storage
30.0 MWWithdrawn / abandoned Kern, CAWest Jan 2018target 2020
Solar project IA-PNM-2012-03, Bernalillo County
Solar
30.0 MWWithdrawn / abandoned Bernalillo, NMWest Aug 2012target 2012
Page 73 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)