Solar project 2018-G3

Solar project 2018-G3 is a 30.0 MW solar request withdrawn in the West interconnection queue, connecting to WAPA Rocky Mountain Region.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2018-G3
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Rocky Mountain Region
Connection point (POI)
Ault 115-kV
Technology
Solar: 30.0 MW
Total requested
30.0 MW
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
15 February 2018
Proposed online date
December 2020

Location

No county location in the queue data.

Power plants in Β· Transmission lines in