πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

SOLAR Β· WEST

Solar project GI-2010-9, Pueblo County

Solar project GI-2010-9, Pueblo County is a 30.0 MW solar request withdrawn in the West interconnection queue, in Pueblo County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2010 (completed)
  2. Withdrawn / abandonedNov 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-2010-9
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Comanche β€šΓ„Γ¬ Fuller β€šΓ„Γ¬ Midway 230 kV line
Location
Pueblo County, Colorado
Technology
Solar: 30.0 MW
Total requested
30.0 MW
Service type
NRIS and ERIS
Study phase
Feasibility Study complete System Impact Study complete Facility Study Underway Request Withdrawn 11/6/12
Queue status
Withdrawn
Entered queue
22 June 2010
Proposed online date
June 2012
Withdrawn
November 2012

Location

Marker shows the centre of Pueblo County; the queue data does not give exact sites.

Power plants in Colorado Β· Transmission lines in Colorado

Other requests in Pueblo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem