πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· WEST

Onshore wind project 2013-G1

Onshore wind project 2013-G1 is a 30.0 MW onshore wind request withdrawn in the West interconnection queue, connecting to WAPA Rocky Mountain Region.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2013-G1
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Rocky Mountain Region
Connection point (POI)
Wray Sub. 115-kV
Technology
Wind: 30.0 MW
Total requested
30.0 MW
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
30 April 2013
Proposed online date
December 2014

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem