United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESProjects with signed interconnection agreements in the USA (2020 requests) β page 7
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Stoneybrook Solar Solar |
19.6 MW | Agreement signed |
| SolarFairfield Solar |
18.1 MW | Agreement signed |
| Emery Meadow Solar Solar |
16.4 MW | Agreement signed |
| Boyles Run Solar Solar |
15.9 MW | Agreement signed |
| Boyles Run Solar Solar |
15.9 MW | Agreement signed |
| South Combe Solar |
15.4 MW | Agreement signed |
| Monmouth Solar 1 Solar |
15.4 MW | Agreement signed |
| Turkey Solar Solar |
14.0 MW | Agreement signed |
| Fields 2 Solar |
13.5 MW | Agreement signed |
| Solar + storage project IC-903, Liberty County Solar + storage |
13.0 MW | Agreement signed |
| Bitter Ridge Wind Farm Onshore wind |
12.6 MW | Agreement signed |
| Union City 34.5 kV Solar |
12.0 MW | Agreement signed |
| Southern Ocean Waretown Solar Solar |
12.0 MW | Agreement signed |
| Juliet Energy Solar Β· Juliet Energy Project, LLC |
12.0 MW | Agreement signed |
| West Lorain 138 kV Power Plant Gas |
11.3 MW | Agreement signed |
| Washington Solar PH II Solar |
11.0 MW | Agreement signed |
| Esky Solar Project Solar |
10.0 MW | Agreement signed |
| SBC Solar Solar + storage |
10.0 MW | Agreement signed |
| Lillie Solar Solar |
9.4 MW | Agreement signed |
| Solar project AF2-088, Clearfield County Solar |
6.5 MW | Agreement signed |
| Naes Battery storage |
5.0 MW | Agreement signed |
| NC3 Ahoskie South Solar Project Solar + storage |
5.0 MW | Agreement signed |
| Geothermal project Company KO, Lyon County Geothermal |
4.8 MW | Agreement signed |
| Hydro project GI-2020-18, Mesa County Hydro |
4.5 MW | Agreement signed |
| RHC Solar Solar + storage |
3.9 MW | Agreement signed |
| GGC Solar Solar + storage |
2.7 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)51 Β· 14.2 GW
- CAISO (California)32 Β· 12.6 GW
- PJM (Mid-Atlantic, Midwest)128 Β· 11.1 GW
- SPP (Southwest Power Pool)25 Β· 5,968 MW
- MISO (Midcontinent)32 Β· 5,106 MW
- West (non-ISO utilities)30 Β· 4,628 MW
- Southeast (non-ISO utilities)24 Β· 4,069 MW
- ISO-NE (New England)4 Β· 129 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)