Withdrawn queue requests in Florida — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown47276.1 GW
Active in queue24.3 GW251 requests
Agreement signed860 MW7 requests
Withdrawn47276.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

472 requests · page 7 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 266, Sumter County
Solar · Masked
74.5 MWWithdrawn / abandoned Sumter, FLSoutheast Sep 2019target 2023
Solar project 287, Manatee County
Solar · Masked
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Jun 2020target 2022
Solar project 166, Hamilton County
Solar · Florida Renewable Partners, LLC
74.5 MWWithdrawn / abandoned Hamilton, FLSoutheast Dec 2016target 2021
Solar project 298, St. Lucie County
Solar · FPL
74.5 MWWithdrawn / abandoned St. Lucie, FLSoutheast Jun 2017target 2028
Solar project 553, Palm Beach County
Solar · FPL
74.5 MWWithdrawn / abandoned Palm Beach, FLSoutheast Jan 2023target 2028
Solar project 512, Manatee County
Solar · FPL
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Jan 2023target 2029
Solar project 586, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2031
Solar project 299, Manatee County
Solar · Masked
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Dec 2021target 2024
Solar project 585, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2031
Solar project 579, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2029
Solar project 8, Manatee County
Solar
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Apr 2017target 2020
Solar project 251, Gadsden County
Solar · Heelstone Energy Holdings, LLC
74.5 MWWithdrawn / abandoned Gadsden, FLSoutheast Apr 2019target 2023
Solar project 576, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2028
Solar project 105, Hillsborough County
Solar
74.5 MWWithdrawn / abandoned Hillsborough, FLSoutheast Jun 2023target 2025
Solar project 26
Solar
74.5 MWWithdrawn / abandoned FLSoutheast Oct 2018target 2020
Solar project 443A, Madison County
Solar · Third Party
74.5 MWWithdrawn / abandoned Madison, FLSoutheast Mar 2022target 2025
Solar project 486, Highlands County
Solar · FPL
74.5 MWWithdrawn / abandoned Highlands, FLSoutheast Jul 2022target 2027
Solar project 480, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2022target 2028
Solar project 572, Charlotte County
Solar · FPL
74.5 MWWithdrawn / abandoned Charlotte, FLSoutheast Jul 2023target 2028
Solar project 295, Alachua County
Solar · FPL
74.5 MWWithdrawn / abandoned Alachua, FLSoutheast Jun 2017target 2029
Solar project IC-621, Jackson County
Solar
74.5 MWWithdrawn / abandoned Jackson, FLSoutheast Apr 2017
Solar project 597, Nassau County
Solar · FPL
74.5 MWWithdrawn / abandoned Nassau, FLSoutheast Jul 2023target 2028
Solar project 44A, Manatee County
Solar
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Jun 2018target 2020
Solar project 64A, Hillsborough County
Solar
74.5 MWWithdrawn / abandoned Hillsborough, FLSoutheast Sep 2019target 2023
Solar project 238, Taylor County
Solar · Fresh Air Energy II, LLC
74.5 MWWithdrawn / abandoned Taylor, FLSoutheast Aug 2018target 2021
Solar project 298, Manatee County
Solar · Masked
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Dec 2021target 2026
Solar project 574, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2028
Solar project 74, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Apr 2020target 2023
Solar project 302, Osceola County
Solar · Masked
74.5 MWWithdrawn / abandoned Osceola, FLSoutheast Jan 2022target 2024
Solar project 580, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2030
Solar project 316, Highlands County
Solar · Masked
74.5 MWWithdrawn / abandoned Highlands, FLSoutheast Aug 2022target 2026
Solar project 192, Manatee County
Solar · FPL
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast May 2016target 2027
Solar project 25
Solar
74.5 MWWithdrawn / abandoned FLSoutheast Oct 2018target 2020
Solar + storage project 329, St Johns County
Solar + storage · Third Party
74.5 MWWithdrawn / abandoned St Johns, FLSoutheast Jan 20182023
Solar project 317, Gadsden County
Solar · Masked
74.5 MWWithdrawn / abandoned Gadsden, FLSoutheast Aug 2022target 2027
Solar project IC-708, Jackson County
Solar
74.5 MWWithdrawn / abandoned Jackson, FLSoutheast May 2018
Solar project 110, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Feb 2024target 2025
Solar project 482, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2022target 2028
Solar project 203B, Osceola County
Solar · Masked
74.5 MWWithdrawn / abandoned Osceola, FLSoutheast Nov 2017target 2020
Solar project 495, Palm Beach County
Solar · FPL
74.5 MWWithdrawn / abandoned Palm Beach, FLSoutheast Jan 2023target 2027
Solar project 443, Manatee County
Solar · FPL
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Mar 2022target 2028
Solar project 170, Columbia County
Solar · Masked
74.5 MWWithdrawn / abandoned Columbia, FLSoutheast Dec 2016target 2018
Solar project JEA-Q001-PV, Nassau County
Solar
74.5 MWWithdrawn / abandoned Nassau, FLSoutheast Oct 2017target 2021
Solar project 584, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2031
Solar project 560, Hendry County
Solar · FPL
74.5 MWWithdrawn / abandoned Hendry, FLSoutheast Jul 2023target 2028
Solar project 479, Highlands County
Solar · FPL
74.5 MWWithdrawn / abandoned Highlands, FLSoutheast Jul 2022target 2028
Solar project 436, Columbia County
Solar · FPL
74.5 MWWithdrawn / abandoned Columbia, FLSoutheast Mar 2022target 2031
Solar project 109, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Oct 2023target 2026
Solar project IC-643, Escambia County
Solar
74.5 MWWithdrawn / abandoned Escambia, FLSoutheast May 2017
Solar project 587, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2032
Page 7 of 10

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)