United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 69

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 69 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AG2-379, Talbot County
Battery storage · Crockett Solar I, LLC
20.0 MWWithdrawn / abandoned Talbot, MDPJM Mar 2021target 2023
Solar project AF1-288, Bedford County
Solar
20.0 MWWithdrawn / abandoned Bedford, PAPJM Sep 2019target 2021
Solar project AF2-420, Boyle County
Solar
20.0 MWWithdrawn / abandoned Boyle, KYPJM Mar 2020target 2021
Solar project W1-009, Accomack County
Solar
20.0 MWWithdrawn / abandoned Accomack, VAPJM Feb 2010target 2011
Solar project AD2-045, Queen Anne's County
Solar
20.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Jan 2018target 2019
Battery storage project AE2-053, Mecklenburg County
Battery storage · RWE Solar Development, LLC
20.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Feb 2019target 2021
Battery storage project AH1-048, Warren County
Battery storage
20.0 MWWithdrawn / abandoned Warren, VAPJM Jul 2021target 2024
Battery storage project AF2-021, Ocean County
Battery storage · Calpine Mid-Atlantic Development, LLC
20.0 MWWithdrawn / abandoned Ocean, NJPJM Nov 2019target 2021
Solar project AE1-017, Pulaski County
Solar
20.0 MWWithdrawn / abandoned Pulaski, VAPJM May 2018target 2020
Solar project AG2-530, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Mar 2021target 2024
Solar project W1-044, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Mar 2010target 2011
Battery storage project AA1-104, Gloucester County
Battery storage
20.0 MWWithdrawn / abandoned Gloucester, NJPJM Oct 2014target 2017
Solar project AD1-096, Ogle County
Solar
20.0 MWWithdrawn / abandoned Ogle, ILPJM Sep 2017target 2018
Solar project AG2-174, Carbon County
Solar
20.0 MWWithdrawn / abandoned Carbon, PAPJM Feb 2021target 2024
Solar + storage project AG2-538, Elk County
Solar + storage · EL-Jakes Hollow LLC
20.0 MWWithdrawn / abandoned Elk, PAPJM Mar 2021target 2022
Solar project AC2-086, Clermont County
Solar
20.0 MWWithdrawn / abandoned Clermont, OHPJM Feb 2017target 2019
Solar project AF1-135, Clearfield County
Solar
20.0 MWWithdrawn / abandoned Clearfield, PAPJM Sep 2019target 2022
Solar project AG2-002, Morrow County
Solar
20.0 MWWithdrawn / abandoned Morrow, OHPJM Oct 2020target 2023
Warfield II
Solar
20.0 MWWithdrawn / abandoned Burlington, NJPJM Sep 2010target 2015
Whitely - Greene Battery Storage Facility
Battery storage
20.0 MWWithdrawn / abandoned Greene, PAPJM Oct 2015target 2019
Solar project AE1-187, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2018target 2021
Solar + storage project AG1-484, Cumberland County
Solar + storage
20.0 MWWithdrawn / abandoned Cumberland, PAPJM Sep 2020target 2024
TWE Chesapeake Solar
Solar
20.0 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Aug 2016target 2018
Solar project AG2-558, Clearfield County
Solar · Morrisdale Solar II, LLC
19.9 MWWithdrawn / abandoned Clearfield, PAPJM Mar 2021target 2023
Gas project AB1-179, Tioga County
Gas
19.9 MWWithdrawn / abandoned Tioga, PAPJM Oct 2015target 2017
Solar project AH1-646, Fayette County
Solar
19.9 MWWithdrawn / abandoned Fayette, PAPJM Sep 2021target 2023
Gas project AA2-080, Washington County
Gas
19.9 MWWithdrawn / abandoned Washington, PAPJM Mar 2015target 2017
Thompson 34.5kV
Gas
19.9 MWWithdrawn / abandoned Susquehanna, PAPJM Apr 2015target 2018
Dan's Mountain Solar Project
Solar
19.9 MWWithdrawn / abandoned Allegany, MDPJM Feb 2014target 2018
Solar project AB2-148, Hertford County
Solar
19.9 MWWithdrawn / abandoned Hertford, NCPJM Apr 2016target 2017
Solar + storage project AD1-149, Kanawha County
Solar + storage
19.9 MWWithdrawn / abandoned Kanawha, WVPJM Sep 2017target 2019
Minster III ESS
Battery storage
19.9 MWWithdrawn / abandoned Auglaize, OHPJM Oct 2016target 2020
Gas project AA2-135, Bradford County
Gas
19.9 MWWithdrawn / abandoned Bradford, PAPJM Apr 2015target 2017
Solar project AF2-313, Queen Anne's County
Solar
19.9 MWWithdrawn / abandoned Queen Anne's, MDPJM Mar 2020target 2021
Gas project AB1-083, Susquehanna County
Gas
19.9 MWWithdrawn / abandoned Susquehanna, PAPJM Sep 2015target 2017
Hop Bottom Generating Station
Gas
19.9 MWWithdrawn / abandoned Lackawanna, PAPJM Oct 2013target 2017
Gas project AA2-167, Bradford County
Gas
19.9 MWWithdrawn / abandoned Bradford, PAPJM Apr 2015target 2017
Niles Valley 34.5kV
Gas
19.9 MWWithdrawn / abandoned Tioga, PAPJM Mar 2015target 2018
Solar project AG1-258, Centre County
Solar
19.9 MWWithdrawn / abandoned Centre, PAPJM Sep 2020target 2023
THP Solar 1
Solar · PA Project 1, LLC
19.9 MWWithdrawn / abandoned Northumberland, PAPJM Sep 2021target 2023
Gas project AA2-112, Susquehanna County
Gas
19.9 MWWithdrawn / abandoned Susquehanna, PAPJM Apr 2015target 2017
Gas project AA1-106, Tioga County
Gas
19.9 MWWithdrawn / abandoned Tioga, PAPJM Oct 2014target 2016
Ten Mile Generation Facility
Gas
19.9 MWWithdrawn / abandoned Washington, PAPJM Apr 2014target 2016
Buckeye Pennsauken Solar Urban Renewal LLC
Solar
19.9 MWWithdrawn / abandoned Camden, NJPJM Aug 2020target 2025
Solar project AH1-332, Armstrong County
Solar
19.9 MWWithdrawn / abandoned Armstrong, PAPJM Sep 2021target 2023
Kiski Valley
Gas
19.9 MWWithdrawn / abandoned Westmoreland, PAPJM Feb 2017target 2020
Amity Generation Facility
Gas
19.9 MWWithdrawn / abandoned Washington, PAPJM Apr 2014target 2017
McLane Solar
Solar · IMG Solar LLC
19.9 MWWithdrawn / abandoned Erie, PAPJM Sep 2021target 2023
Gas project AA2-134, Washington County
Gas
19.9 MWWithdrawn / abandoned Washington, PAPJM Apr 2015target 2017
Solar + storage project AG1-479, Grundy County
Solar + storage
19.9 MWWithdrawn / abandoned Grundy, ILPJM Sep 2020target 2023
Page 69 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)