United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 69
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project AG2-379, Talbot County Battery storage · Crockett Solar I, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AF1-288, Bedford County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AF2-420, Boyle County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project W1-009, Accomack County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AD2-045, Queen Anne's County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AE2-053, Mecklenburg County Battery storage · RWE Solar Development, LLC |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-048, Warren County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AF2-021, Ocean County Battery storage · Calpine Mid-Atlantic Development, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AE1-017, Pulaski County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-530, Salem County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project W1-044, Franklin County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AA1-104, Gloucester County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AD1-096, Ogle County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-174, Carbon County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AG2-538, Elk County Solar + storage · EL-Jakes Hollow LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AC2-086, Clermont County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AF1-135, Clearfield County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-002, Morrow County Solar |
20.0 MW | Withdrawn / abandoned |
| Warfield II Solar |
20.0 MW | Withdrawn / abandoned |
| Whitely - Greene Battery Storage Facility Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AE1-187, Adams County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AG1-484, Cumberland County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| TWE Chesapeake Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-558, Clearfield County Solar · Morrisdale Solar II, LLC |
19.9 MW | Withdrawn / abandoned |
| Gas project AB1-179, Tioga County Gas |
19.9 MW | Withdrawn / abandoned |
| Solar project AH1-646, Fayette County Solar |
19.9 MW | Withdrawn / abandoned |
| Gas project AA2-080, Washington County Gas |
19.9 MW | Withdrawn / abandoned |
| Thompson 34.5kV Gas |
19.9 MW | Withdrawn / abandoned |
| Dan's Mountain Solar Project Solar |
19.9 MW | Withdrawn / abandoned |
| Solar project AB2-148, Hertford County Solar |
19.9 MW | Withdrawn / abandoned |
| Solar + storage project AD1-149, Kanawha County Solar + storage |
19.9 MW | Withdrawn / abandoned |
| Minster III ESS Battery storage |
19.9 MW | Withdrawn / abandoned |
| Gas project AA2-135, Bradford County Gas |
19.9 MW | Withdrawn / abandoned |
| Solar project AF2-313, Queen Anne's County Solar |
19.9 MW | Withdrawn / abandoned |
| Gas project AB1-083, Susquehanna County Gas |
19.9 MW | Withdrawn / abandoned |
| Hop Bottom Generating Station Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AA2-167, Bradford County Gas |
19.9 MW | Withdrawn / abandoned |
| Niles Valley 34.5kV Gas |
19.9 MW | Withdrawn / abandoned |
| Solar project AG1-258, Centre County Solar |
19.9 MW | Withdrawn / abandoned |
| THP Solar 1 Solar · PA Project 1, LLC |
19.9 MW | Withdrawn / abandoned |
| Gas project AA2-112, Susquehanna County Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AA1-106, Tioga County Gas |
19.9 MW | Withdrawn / abandoned |
| Ten Mile Generation Facility Gas |
19.9 MW | Withdrawn / abandoned |
| Buckeye Pennsauken Solar Urban Renewal LLC Solar |
19.9 MW | Withdrawn / abandoned |
| Solar project AH1-332, Armstrong County Solar |
19.9 MW | Withdrawn / abandoned |
| Kiski Valley Gas |
19.9 MW | Withdrawn / abandoned |
| Amity Generation Facility Gas |
19.9 MW | Withdrawn / abandoned |
| McLane Solar Solar · IMG Solar LLC |
19.9 MW | Withdrawn / abandoned |
| Gas project AA2-134, Washington County Gas |
19.9 MW | Withdrawn / abandoned |
| Solar + storage project AG1-479, Grundy County Solar + storage |
19.9 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)