Completed queue projects in the USA (2015 requests) β€” page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown27237.2 GW
Active in queue15.8 GW73 requests
Agreement signed8,536 MW38 requests
Withdrawn80095.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

272 requests Β· page 6 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Oak Street Landfill Solar Project
Solar
2.3 MWOperating Atlantic, NJPJM May 20152020
Solar project 203, Stillwater County
Solar
2.0 MWOperating Stillwater, MTWest Apr 20152016
West Caldwell Solar
Solar + storage
2.0 MWOperating Essex, NJPJM Jun 20152018
Balls Gap Battery Facility
Battery storage
2.0 MWOperating Cabell, WVPJM Aug 20152017
Other project J469, Crawford County
Other
2.0 MWOperating Crawford, MIMISO Jun 20152017
Solar project 639, Tooele County
Solar Β· Dugway Proving Ground
2.0 MWOperating Tooele, UTWest Jan 2015target 2016
Solar project 666, Umatilla County
Solar Β· Pilot Rock Solar 1. LLC
2.0 MWOperating Umatilla, ORWest May 2015target 2025
Princeton Hospital NRG Energy Center
Gas
2.0 MWOperating Mercer, NJPJM Feb 20152017
Kendall Reconfiguration Project
Gas
1.9 MWOperating Middlesex, MAISO-NE Jan 2015target 2016
Hydro project 494, Lincoln County
Hydro
1.2 MWOperating Lincoln, IDWest May 2015target 2016
Kingsville Solar
Solar
1.1 MWOperating Harford, MDPJM Mar 20152016
Hopewell Valley Solar
Solar + storage
1.0 MWOperating Mercer, NJPJM Feb 20152015
UEC Solar PV Array
Solar
1.0 MWOperating Umatilla, ORWest Apr 2015target 2015
Dovetail Biogas Facility
Other
0.9 MWOperating Greene, OHPJM Oct 20152016
Gas project AB1-116, Atlantic County
Gas
0.8 MWOperating Atlantic, NJPJM Oct 20152018
Tansboro Road
Gas
0.7 MWOperating Camden, NJPJM Oct 20152018
Cooper Solar
Solar + storage
0.4 MWOperating Camden, NJPJM Sep 20152017
Solar project 45
Solar
0.4 MWOperating West Jun 20152015
Hydro project 677, Johnson County
Hydro Β· City of Buffalo
0.2 MWOperating Johnson, WYWest Jun 2015target 2016
Hydro project 469, Jerome County
Hydro
0.2 MWOperating Jerome, IDWest Mar 2015target 2015
Hydro project 468, Jerome County
Hydro
0.1 MWOperating Jerome, IDWest Mar 2015target 2015
Gas project 646, Fremont County
Gas Β· American Industrial Laundry
0.0 MWOperating Fremont, WYWest Mar 2015target 2016
Page 6 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)