🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Mexico

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in New Mexico — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown40758.7 GW
Active in queue34.0 GW164 requests
Agreement signed8,278 MW53 requests
Withdrawn40758.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

407 requests · page 6 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Q182, San Juan County
Solar
50.0 MWWithdrawn / abandoned San Juan, NMWest Jan 2011target 2013
Solar + storage project GEN-2021-083, Chaves County
Solar + storage
50.0 MWWithdrawn / abandoned Chaves, NMSPP Apr 20212024
Solar + storage project IA-PNM-2020-18, Bernalillo County
Solar + storage
49.9 MWWithdrawn / abandoned Bernalillo, NMWest Oct 2020target 2022
Solar project IA-PNM-2022-07, Grant County
Solar
49.9 MWWithdrawn / abandoned Grant, NMWest Apr 2022target 2024
Solar project IA-PNM-2017-19, Valencia County
Solar
49.9 MWWithdrawn / abandoned Valencia, NMWest Oct 2017target 2020
Solar project IA-PNM-2017-23, Cibola County
Solar
49.9 MWWithdrawn / abandoned Cibola, NMWest Oct 2017target 2022
Palace Solar
Solar
49.0 MWWithdrawn / abandoned Valencia Cty, NMWest Nov 2014target 2016
Solar project IA-PNM-2016-03, Valencia County
Solar
49.0 MWWithdrawn / abandoned Valencia, NMWest Nov 2016target 2019
Solar project IA-PNM-2014-08, Valencia Cty County
Solar
49.0 MWWithdrawn / abandoned Valencia Cty, NMWest Nov 2014target 2016
Solar project GEN-2019-022, Lea County
Solar
41.0 MWWithdrawn / abandoned Lea, NMSPP Apr 20192024
Solar project GEN-2014-047, Roosevelt County
Solar
40.0 MWWithdrawn / abandoned Roosevelt, NMSPP Sep 20142017
Other project IA-PNM-2004-02, Torrance County
Other
37.0 MWWithdrawn / abandoned Torrance, NMWest Jul 2004target 2012
Solar + storage project IA-PNM-2019-21, Santa Fe County
Solar + storage
36.0 MWWithdrawn / abandoned Santa Fe, NMWest Apr 2019target 2021
Solar project GEN-2008-102, Chaves County
Solar
34.2 MWWithdrawn / abandoned Chaves, NMSPP Aug 2008target 2010
Solar project GEN-2008-101, Lea County
Solar
34.2 MWWithdrawn / abandoned Lea, NMSPP Aug 2008target 2010
Solar project GEN-2017-016, Quay County
Solar
33.0 MWWithdrawn / abandoned Quay, NMSPP May 20172023
Solar project GEN-2016-069, Chaves County
Solar
31.4 MWWithdrawn / abandoned Chaves, NMSPP Mar 2016target 2018
Battery storage project IA-PNM-2020-02, Bernalillo County
Battery storage
30.0 MWWithdrawn / abandoned Bernalillo, NMWest Jan 2020target 2022
Solar project GEN-2012-022, Lea County
Solar
30.0 MWWithdrawn / abandoned Lea, NMSPP Sep 2012target 2014
Solar project IA-PNM-2012-03, Bernalillo County
Solar
30.0 MWWithdrawn / abandoned Bernalillo, NMWest Aug 2012target 2012
Solar project GEN-2014-066, Quay County
Solar
30.0 MWWithdrawn / abandoned Quay, NMSPP Sep 2014target 2016
Solar project GEN-2012-015, Quay County
Solar
26.0 MWWithdrawn / abandoned Quay, NMSPP Jul 2012target 2014
Solar + storage project IA-PNM-2019-23, Luna County
Solar + storage
24.0 MWWithdrawn / abandoned Luna, NMWest Apr 2019target 2021
Solar project GEN-2009-067S, Eddy County
Solar
20.0 MWWithdrawn / abandoned Eddy, NMSPP Dec 2009target 2010
Solar project GEN-2023-187, Eddy County
Solar
20.0 MWWithdrawn / abandoned Eddy, NMSPP Oct 20232023
V20S
Solar
20.0 MWWithdrawn / abandoned Dona Ana, NMWest Feb 2017target 2019
Solar project GEN-2010-058, Chaves County
Solar
20.0 MWWithdrawn / abandoned Chaves, NMSPP Nov 2010target 2011
Solar project SGI-PNM-2013-09, Santa Fe County
Solar
20.0 MWWithdrawn / abandoned Santa Fe, NMWest Dec 2013target 2016
AN20S Project
Solar
20.0 MWWithdrawn / abandoned Dona Ana, NMWest Mar 2019target 2020
Solar project GEN-2010-020, Chaves County
Solar
20.0 MWWithdrawn / abandoned Chaves, NMSPP Mar 2010target 2011
Solar project GEN-2010-021, Eddy County
Solar
20.0 MWWithdrawn / abandoned Eddy, NMSPP Mar 2010target 2011
NM Tularosa Solar Project (Lincoln Renewable Energy LLC)
Solar
20.0 MWWithdrawn / abandoned Otero, NMWest May 2012target 2014
Solar project SGI-PNM-2013-08, Bernalillo County
Solar
10.0 MWWithdrawn / abandoned Bernalillo, NMWest Nov 2013target 2015
Solar project SGI-PNM-2013-06, Valencia Cty County
Solar
10.0 MWWithdrawn / abandoned Valencia Cty, NMWest Nov 2013target 2015
Solar project SGI-PNM-2016-03, Sandoval County
Solar
10.0 MWWithdrawn / abandoned Sandoval, NMWest Nov 2016target 2019
Solar project SGI-PNM-2014-10, Bernalillo County
Solar
10.0 MWWithdrawn / abandoned Bernalillo, NMWest Nov 2014target 2015
Solar project SGI-PNM-2014-02, Santa Fe County
Solar
10.0 MWWithdrawn / abandoned Santa Fe, NMWest Jan 2014target 2015
Solar project SGI-PNM-2017-07, Santa Fe County
Solar
10.0 MWWithdrawn / abandoned Santa Fe, NMWest Jun 2017target 2018
Solar project SGI-PNM-2016-02, Sandoval County
Solar
10.0 MWWithdrawn / abandoned Sandoval, NMWest Nov 2016target 2019
Solar project SGI-PNM-2011-04, Valencia County
Solar
10.0 MWWithdrawn / abandoned Valencia, NMWest Jun 2011target 2013
Solar project SGI-PNM-2021-34, Otero County
Solar
10.0 MWWithdrawn / abandoned Otero, NMWest Jul 2021target 2022
Solar project SGI-PNM-2017-01, Luna County
Solar
10.0 MWWithdrawn / abandoned Luna, NMWest Jan 2017target 2018
Deming Solar Project
Solar · Deming Solar Project LLC
9.0 MWWithdrawn / abandoned Luna, NMWest Sep 2013target 2017
Solar project SGI-PNM-2017-03, Santa Fe County
Solar
9.0 MWWithdrawn / abandoned Santa Fe, NMWest Mar 2017target 2018
Solar project SGI-PNM-2013-01, Valencia County
Solar
9.0 MWWithdrawn / abandoned Valencia, NMWest May 2013target 2014
NM Solar 1 LLC
Solar
8.0 MWWithdrawn / abandoned Bernalillo Cty, NMWest Sep 2011target 2014
Solar project SGI-PNM-2017-02, Luna County
Solar
7.5 MWWithdrawn / abandoned Luna, NMWest Jan 2017target 2018
Solar project SGI-PNM-2014-07
Solar
6.0 MWWithdrawn / abandoned NMWest Aug 2014target 2015
Solar project SGI-PNM-2021-47, Hidalgo County
Solar
5.0 MWWithdrawn / abandoned Hidalgo, NMWest Aug 2021target 2022
Solar project SGI-PNM-2021-48, Hidalgo County
Solar
5.0 MWWithdrawn / abandoned Hidalgo, NMWest Aug 2021target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)