United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

SOLAR Β· SPP

Solar project GEN-2017-016, Quay County

Solar project GEN-2017-016, Quay County is a 33.0 MW solar request withdrawn in the SPP interconnection queue, in Quay County, New Mexico, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedMay 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2023 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-016
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Norton 115 kV Switching Station
Location
Quay County, New Mexico
Technology
Solar: 33.0 MW
Total requested
33.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 May 2017
Proposed online date
December 2023
Came online
December 2023
Withdrawn
May 2021

Location

Marker shows the centre of Quay County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Quay County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem