United States › Grid › Interconnection queues › New Mexico
ONSHORE WIND · SPPOnshore wind project GEN-2023-GR3, Quay County
Onshore wind project GEN-2023-GR3, Quay County is a 80.0 MW onshore wind request built and operating in the SPP interconnection queue, in Quay County, New Mexico, connecting to Xcel/SPS.
Request details
- Queue ID
- GEN-2023-GR3
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- Xcel/SPS
- Connection point (POI)
- Norton 115 kV
- Location
- Quay County, New Mexico
- Technology
- Wind: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 30 June 2023
- Came online
- December 2024
Location
Marker shows the centre of Quay County; the queue data does not give exact sites.
Power plants in New Mexico · Transmission lines in New Mexico
Other requests in Quay County
- Casa Mesa WindOnshore wind · 51.0 MW · built
- Solar project GEN-2013-022, Quay CountySolar · 25.0 MW · built
- Gas project GEN-2011-046, Quay CountyGas · 23.0 MW · built
- Solar project GEN-2023-095, Quay CountySolar · 850 MW · withdrawn
- Battery storage project GEN-2020-080, Quay CountyBattery storage · 200 MW · withdrawn
- Onshore wind project GEN-2023-096, Quay CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GEN-2001-036, Quay CountyOnshore wind · 80.0 MW · withdrawn
- Onshore wind project GEN-2003-003, Quay CountyOnshore wind · 80.0 MW · withdrawn
- Solar project GEN-2017-016, Quay CountySolar · 33.0 MW · withdrawn
- Solar project GEN-2014-066, Quay CountySolar · 30.0 MW · withdrawn
- Solar project GEN-2012-015, Quay CountySolar · 26.0 MW · withdrawn
- Solar project GEN-2017-069, Quay CountySolar · 1.8 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem