SOLAR Β· WEST

V20S

V20S is a 20.0 MW solar request withdrawn in the West interconnection queue, in Dona Ana County, New Mexico, connecting to El Paso Electric Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2017 (completed)
  2. Withdrawn / abandonedDec 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
SG-17-2-1
Grid region
West (non-ISO utilities)
Utility / transmission owner
El Paso Electric Company
Connection point (POI)
Verde 24 kV bus (planned)
Location
Dona Ana County, New Mexico
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
28 February 2017
Proposed online date
June 2019
Withdrawn
December 2017

Location

Marker shows the centre of Dona Ana County; the queue data does not give exact sites.