United States › Grid › Interconnection queues › New Mexico

SOLAR + STORAGE · WEST

D150S Project

D150S Project is a 150 MW solar + storage request suspended in the West interconnection queue, in Dona Ana County, New Mexico, connecting to El Paso Electric Company.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2017 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2020 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
LG-17-9-1
Grid region
West (non-ISO utilities)
Utility / transmission owner
El Paso Electric Company
Connection point (POI)
Diablo 115 kV Substation
Location
Dona Ana County, New Mexico
Technology
Solar: 150 MW · Battery
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
LGIA in effect
Queue status
Suspended
Entered queue
6 September 2017
Proposed online date
September 2020

Location

Marker shows the centre of Dona Ana County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Dona Ana County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem