Withdrawn queue requests in Nevada — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown35588.4 GW
Active in queue81.5 GW249 requests
Agreement signed20.9 GW82 requests
Withdrawn35588.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

355 requests · page 6 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Company IM, Washoe County
Solar + storage
80.0 MWWithdrawn / abandoned Washoe, NVWest Mar 2018target 2020
Solar project Company 132, Clark County
Solar
80.0 MWWithdrawn / abandoned Clark, NVWest Mar 2014target 2016
Geothermal project 263, Elko County
Geothermal
75.0 MWWithdrawn / abandoned Elko, NVWest Jul 2008target 2010
Warren Solar 1
Solar
71.5 MWWithdrawn / abandoned Nye, NVCAISO May 2017target 2020
Solar project Company HB, Pershing County
Solar
70.0 MWWithdrawn / abandoned Pershing, NVWest Mar 2016target 2024
Coyote Canyon
Geothermal
70.0 MWWithdrawn / abandoned Churchill, NVCAISO Mar 2011target 2013
Solar + storage project Company JD, Humboldt County
Solar + storage
70.0 MWWithdrawn / abandoned Humboldt, NVWest Sep 2018target 2021
Battery storage project Company IX, Pershing County
Battery storage
70.0 MWWithdrawn / abandoned Pershing, NVWest Sep 2018target 2024
Solar project Company GL, Pershing County
Solar
70.0 MWWithdrawn / abandoned Pershing, NVWest Mar 2015target 2024
Desert Obsidian
Solar
67.2 MWWithdrawn / abandoned Clark, NVCAISO May 2016target 2020
Sunshine Valley Solar 3
Solar
65.0 MWWithdrawn / abandoned Nye, NVCAISO Apr 2014target 2017
Green Borders Geothermal
Geothermal
62.0 MWWithdrawn / abandoned Mineral, NVCAISO Feb 2005target 2012
NYC #1
Geothermal
60.7 MWWithdrawn / abandoned Churchill, NVCAISO May 2008target 2015
TGDV #1
Geothermal
60.7 MWWithdrawn / abandoned Churchill, NVCAISO May 2008target 2012
TGDV#2
Geothermal
60.7 MWWithdrawn / abandoned Churchill, NVCAISO May 2008target 2013
Dixie Meadows #1
Geothermal
60.7 MWWithdrawn / abandoned Churchill, NVCAISO May 2008target 2016
Solar project Company GO, Lyon County
Solar
60.0 MWWithdrawn / abandoned Lyon, NVWest Mar 2015target 2016
Solar project Company GN, Pershing County
Solar
60.0 MWWithdrawn / abandoned Pershing, NVWest Mar 2015target 2017
Solar project Company 121, Clark County
Solar
58.0 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2016
Solar project Company 126, Clark County
Solar
58.0 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2016
Solar project Company 91, Clark County
Solar
55.0 MWWithdrawn / abandoned Clark, NVWest Apr 2010target 2011
NYC #2
Geothermal
52.5 MWWithdrawn / abandoned Churchill, NVCAISO May 2008target 2012
Dixie Meadows #2
Geothermal
52.5 MWWithdrawn / abandoned Churchill, NVCAISO May 2008target 2013
Solar project Company 118, Clark County
Solar
51.0 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2015
Solar project Company 80, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Sep 2009target 2010
Solar project Company 122, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2016
Solar project Company 135, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Sep 2014target 2017
Solar project Company 83, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Oct 2009target 2011
Battery storage project Company 187, Clark County
Battery storage
50.0 MWWithdrawn / abandoned Clark, NVWest Sep 2019target 2022
Solar project Company HH, Pershing County
Solar
50.0 MWWithdrawn / abandoned Pershing, NVWest Sep 2016target 2020
Solar project Company 98, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Dec 2010target 2016
Solar project Company GE, Nye County
Solar
50.0 MWWithdrawn / abandoned Nye, NVWest Mar 2015target 2016
Roadrunner
Solar
50.0 MWWithdrawn / abandoned Nye, NVCAISO Apr 2014target 2019
Solar project Company II, Pershing County
Solar
50.0 MWWithdrawn / abandoned Pershing, NVWest Mar 2018target 2024
Caballo Loco
Solar
50.0 MWWithdrawn / abandoned Nye, NVCAISO Apr 2014target 2019
Solar project Company 128, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2025
Battery storage project Company 175, Clark County
Battery storage
50.0 MWWithdrawn / abandoned Clark, NVWest Mar 2019target 2023
Solar project Company 134, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Sep 2014target 2016
Solar project Company 111, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Sep 2011target 2014
Battery storage project Company JW1, Washoe County
Battery storage
50.0 MWWithdrawn / abandoned Washoe, NVWest Mar 2019target 2023
Solar project Company 97, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Oct 2010target 2012
Gas project Company JF, Esmerelda County
Gas
48.0 MWWithdrawn / abandoned Esmerelda, NVWest Sep 2018target 2021
Geothermal project Company JG, Washoe County
Geothermal
45.0 MWWithdrawn / abandoned Washoe, NVWest Sep 2018target 2021
Geothermal project Company HO, Pershing County
Geothermal
45.0 MWWithdrawn / abandoned Pershing, NVWest Sep 2017target 2026
Other project Company 150, Clark County
Other
43.5 MWWithdrawn / abandoned Clark, NVWest Mar 2016target 2021
Battery storage project Company 241, Clark County
Battery storage
40.0 MWWithdrawn / abandoned Clark, NVWest Feb 2023target 2025
Solar + storage project Company JR, Lander County
Solar + storage
40.0 MWWithdrawn / abandoned Lander, NVWest Feb 2019target 2021
Geothermal project Company FU, Lander County
Geothermal
38.5 MWWithdrawn / abandoned Lander, NVWest Sep 2013target 2015
Geothermal project Company HF, Lander County
Geothermal
38.5 MWWithdrawn / abandoned Lander, NVWest May 2016target 2019
Geothermal project Company HW, Esmerelda County
Geothermal
38.5 MWWithdrawn / abandoned Esmerelda, NVWest Sep 2017target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)