United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 4 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project Q468, Maricopa County
Battery storage
1,000 MWIn study Maricopa, AZWest Mar 2022target 2025
Gas project 25-00427, Storey County
Gas
1,000 MWIn study Storey, NVWest Jul 2025target 2028
Solar + storage project Q474, Maricopa County
Solar + storage
1,000 MWIn study Maricopa, AZWest Mar 2022target 2025
Solar + storage project G1087, Yakima County
Solar + storage
1,000 MWIn study Yakima, WAWest Dec 2025target 2031
Solar + storage project Q379, Maricopa County
Solar + storage
1,000 MWPaused / redesign Maricopa, AZWest Mar 2021target 2024
Wind + storage project Q101, Los Angeles County
Wind + storage
1,000 MWIn study Los Angeles, CAWest Apr 2023target 2030
Solar + storage project 662, Power County
Solar + storage · Sawtooth DevCo, LLC
1,000 MWPaused / redesign Power, IDWest Jun 2022target 2027
Solar + storage project 661, Sweetwater County
Solar + storage · Sawtooth DevCo, LLC
1,000 MWPaused / redesign Sweetwater, WYWest Jun 2022target 2027
Solar + storage project Q93, Millard County
Solar + storage · Intermountain Power Agency
1,000 MWIn study Millard, UTWest Aug 2022target 2025
Other project 635, Gooding County
Other · Taurus Wind LLC
1,000 MWPaused / redesign Gooding, IDWest Feb 2022target 2029
Solar + storage project Q97, Los Angeles County
Solar + storage
1,000 MWIn study Los Angeles, CAWest Mar 2023target 2030
Solar project Q274, Coconino County
Solar
1,000 MWIn study Coconino, AZWest Mar 2018target 2024
Onshore wind project Q318, San Juan County
Onshore wind
1,000 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Solar project AH2-351
Solar
1,000 MWIn study KYPJM Mar 2022target 2027
Solar project AH2-353
Solar
1,000 MWIn study KYPJM Mar 2022target 2028
Solar + storage project Q466, Yuma County
Solar + storage
1,000 MWIn study Yuma, AZWest Mar 2022target 2025
Wind + storage project Q100, Los Angeles County
Wind + storage
1,000 MWIn study Los Angeles, CAWest Apr 2023target 2030
Onshore wind project Q319, San Juan County
Onshore wind
1,000 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Battery storage project Q112, San Bernardino County
Battery storage
1,000 MWIn study San Bernardino, CAWest Oct 2024target 2028
Solar + storage project 125, Apache County
Solar + storage
1,000 MWIn study Apache, AZWest Jun 2022target 2025
Solar + storage project Q88, Clark County
Solar + storage
1,000 MWIn study Clark, NVWest Apr 2022target 2028
Solar + storage project G0657, Klamath County
Solar + storage
1,000 MWIn study Klamath, ORWest Sep 2020target 2027
Kickstart Energy Storage V
Battery storage · Kickstart Infrastructure LLC
999 MWIn study Ellis, TXERCOT Nov 2025target 2029
Black Mountain Hale Gas
Gas · Fort Worth Power Core LLC
991 MWIn study Hale, TXERCOT Aug 2025target 2029
Gas project G0760, Grant County
Gas
990 MWIn study Grant, WAWest Jun 2022target 2025
Gas project 977454, Anson County
Gas
990 MWIn study Anson, NCSoutheast Jun 2025
Zeus Spade Wind
Wind + storage · Spade Wind, LLC
987 MWIn study Mitchell, TXERCOT Mar 2024target 2027
Gas project E0050, Linn County
Gas · Interstate Power and Light Company (IPL)
987 MWIn study Linn, IAMISO Nov 2025target 2028
Complex Serenity Wind
Onshore wind · Serenity Wind, LLC
971 MWIn study Armstrong, TXERCOT Jun 2025target 2029
Kilby1 Part 4 Large Block Simple Cycle
Gas · Energy Forge One LLC
950 MWIn study Reeves, TXERCOT Nov 2025target 2028
Gas project J4116, Walworth County
Gas
950 MWIn study Walworth, WIMISO Oct 2025target 2030
Riviera Gas
Gas · BKV-BPP Power
942 MWIn study Bell, TXERCOT Nov 2025target 2030
Gas project Q32, Pinal County
Gas
928 MWIn study Pinal, AZWest Aug 2023target 2026
Bristlecone
Solar + storage
921 MWIn study Nye, NVCAISO Apr 2023target 2030
Gas project GEN-2023-204, Morris County
Gas
915 MWIn study Morris, TXSPP Oct 2023target 2028
Gas project GEN-2024-129, Labette County
Gas
910 MWIn study Labette, KSSPP Mar 2025target 2030
Hoodini
Solar + storage
910 MWIn study Yuma, AZCAISO Apr 2019target 2028
Arida 3 Solar Farm
Solar + storage
900 MWIn study Clark, NVCAISO Apr 2020target 2030
Solar project G0687, Sherman County
Solar
900 MWIn study Sherman, ORWest Aug 2021target 2024
Solar + storage project 25-00432, Lyon County
Solar + storage
900 MWIn study Lyon, NVWest Jul 2025target 2029
Fierce River Solar
Solar + storage · Rio Grande Solar LLC
896 MWIn study Starr, TXERCOT Mar 2024target 2029
West Royal Natural Gas (TEF-Due Diligence)
Gas · Invenergy Energy Transition Development LLC
888 MWIn study Upton, TXERCOT Jun 2024target 2030
Sim Gideon Combined Cycle
Gas · LCRA
880 MWIn study Bastrop, TXERCOT Jun 2025target 2030
Lost Pines Power Park
Gas · LCRA
880 MWIn study Bastrop, TXERCOT Jun 2025target 2030
Schneider Combined Cycle
Gas · LCRA
880 MWIn study Caldwell, TXERCOT Jul 2025target 2030
Sunrise Wind
Offshore wind · Sunrise Wind LLC
880 MWIn study Suffolk, NYNYISO Sep 2018target 2027
Invictus
Solar + storage
860 MWIn study Riverside, CACAISO Apr 2021target 2029
Nuclear project AH1-695, Dauphin County
Nuclear · Constellation Energy Generation, LLC
859 MWIn study Dauphin, PAPJM Apr 2025
MilamStation Power Secured Gas Generation
Gas · Power Secured Holdings LLC
846 MWIn study Milam, TXERCOT Mar 2025target 2029
Solar + storage project Q2417, Maricopa County
Solar + storage
843 MWIn study Maricopa, AZWest Feb 2024target 2028
Page 4 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)