United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in the USA (2020 requests) β€” page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown18115.9 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

181 requests Β· page 4 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Bowman Street 115 kV SS - Augusta Area Study
Solar
3.3 MWOperating Kennebec, MEISO-NE Oct 2020target 2022
Northwest Ohio Wind
Solar + storage
3.2 MWOperating Paulding, OHPJM Mar 20202021
Other project 576, Gooding County
Other Β· West Point RNG LLC
3.2 MWOperating Gooding, IDWest Jan 20202024
Qualco Project
Other
3.0 MWOperating Snohomish, WAWest Oct 2020target 2021
Hydro project 579, Twin Falls County
Hydro Β· Lateral 10 Venture
2.6 MWOperating Twin Falls, IDWest Apr 2020target 2020
Hydro project 596, Twin Falls County
Hydro Β· Crystal Springs Hydroelectric, L.P.
2.5 MWOperating Twin Falls, IDWest Jun 2020target 2021
Fairhaven Battery Energy Storage System
Battery storage
2.5 MWOperating Anne Arundel, MDPJM Jul 20202024
Cranberry Highway Solar + Battery Storage
Solar + storage
2.2 MWOperating Plymouth, MAISO-NE Apr 2020target 2022
Kumquat Solar
Solar
2.0 MWOperating Wicomico, MDPJM Mar 20202022
Hydro project 398, Cascade County
Hydro
2.0 MWOperating Cascade, MTWest Nov 20202021
Other project AF2-152, Charles County
Other
2.0 MWOperating Charles, MDPJM Mar 2020target 2021
Chalk Point CT 2
Gas
2.0 MWOperating Prince George's, MDPJM Mar 20202023
Other project AF2-153, Charles County
Other
2.0 MWOperating Charles, MDPJM Mar 2020target 2021
Point Wind Fast Track
Onshore wind
1.6 MWOperating Kern, CACAISO Apr 20202021
Wyalusing 34.5 kV
Gas
1.5 MWOperating Bradford, PAPJM Mar 20202021
Oxbow Creek Energy
Gas
1.5 MWOperating Wyoming, PAPJM Mar 20202021
Solar project 75, Hillsborough County
Solar
1.0 MWOperating Hillsborough, FLSoutheast Sep 2020target 2020
Chesapeake Beach BESS
Battery storage
1.0 MWOperating Calvert, MDPJM Nov 20202023
Hydro project 584, Twin Falls County
Hydro Β· Russell LeMoyne
0.8 MWOperating Twin Falls, IDWest Jun 2020target 2020
Hydro project 594, Twin Falls County
Hydro Β· J.M. Miller Enterprises, Inc.
0.6 MWOperating Twin Falls, IDWest Jan 2020target 2020
Hydro project 581, Twin Falls County
Hydro Β· Sagebrush Hydro
0.6 MWOperating Twin Falls, IDWest May 2020target 2020
Hydro project 600, Lemhi County
Hydro Β· Lemhi Hydropower Company
0.5 MWOperating Lemhi, IDWest Oct 2020target 2021
Hydro project 582, Twin Falls County
Hydro Β· Jim Knight Hydro
0.5 MWOperating Twin Falls, IDWest May 2020target 2020
Rock River ESS
Battery storage
0.5 MWOperating Whiteside, ILPJM Jul 20202021
Hydro project 583, Blaine County
Hydro Β· White Water Power Company, Inc
0.4 MWOperating Blaine, IDWest May 2020target 2020
Bridgeport Harbor Unit #5 Uprate
Gas
0.4 MWOperating Fairfield, CTISO-NE Mar 2020target 2021
Hydro project 593, Twin Falls County
Hydro Β· Shawpatin Ag Cap LLC.
0.3 MWOperating Twin Falls, IDWest Dec 2020target 2020
Hydro project 589, Twin Falls County
Hydro Β· Scott Kaster
0.3 MWOperating Twin Falls, IDWest Sep 2020target 2020
Other project 592, Bannock County
Other Β· City of Pocatello
0.3 MWOperating Bannock, IDWest Dec 2020target 2020
Hydro project 586, Twin Falls County
Hydro Β· White Water Power Company
0.2 MWOperating Twin Falls, IDWest Jul 2020target 2020
Rumford Power Repair for Performance Upgrade
Gas
0.2 MWOperating Oxford, MEISO-NE Mar 2020target 2021
Page 4 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)