United States › Grid › Interconnection queues › California

ONSHORE WIND · CAISO

Point Wind Fast Track

Point Wind Fast Track is a 1.6 MW onshore wind request built and operating in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Apr 2020 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMar 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1679
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Vincent Sub
Location
Kern County, California
Technology
Wind: 1.6 MW
Total requested
1.6 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Operational
Entered queue
14 April 2020
Proposed online date
November 2020
Came online
March 2021

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem