Queue requests in study in Washington — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown18055.0 GW
Active in queue58.5 GW207 requests
Agreement signed3,095 MW26 requests
Withdrawn499103.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

180 requests · page 4 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project G0717, Klickitat County
Battery storage
75.0 MWIn study Klickitat, WAWest Dec 2021target 2024
Solar project G1010, Yakima County
Solar
70.0 MWIn study Yakima, WAWest Nov 2023target 2027
Solar + storage project Q59, Adams County
Solar + storage
60.0 MWPaused / redesign Adams, WAWest
Battery storage project G1076, Yakima County
Battery storage
46.5 MWIn study Yakima, WAWest Mar 2025target 2027
Solar project 103, Lincoln County
Solar
40.0 MWIn study Lincoln, WAWest Dec 2019target 2021
Battery storage project G0733, Benton County
Battery storage
30.0 MWIn study Benton, WAWest Mar 2022target 2025
Battery storage project G0832, Snohomish County
Battery storage
25.0 MWIn study Snohomish, WAWest Dec 2022target 2025
Battery storage project G0734, Benton County
Battery storage
20.0 MWIn study Benton, WAWest Mar 2022target 2024
Battery storage project G0830, Thurston County
Battery storage
20.0 MWIn study Thurston, WAWest Dec 2022target 2026
Battery storage project G0942, Thurston County
Battery storage
20.0 MWIn study Thurston, WAWest Sep 2023target 2026
Battery storage project G1058, Clark County
Battery storage
20.0 MWIn study Clark, WAWest Dec 2023target 2027
Battery storage project G0829, Douglas County
Battery storage
20.0 MWIn study Douglas, WAWest Dec 2022target 2026
Solar + storage project 80, Spokane County
Solar + storage
19.0 MWIn study Spokane, WAWest Dec 2018target 2025
Onshore wind project G0721, Benton County
Onshore wind
13.6 MWIn study Benton, WAWest Dec 2021target 2024
Solar project G0689, Franklin County
Solar
13.3 MWIn study Franklin, WAWest Sep 2021target 2023
Battery storage project G1079, Franklin County
Battery storage
10.0 MWIn study Franklin, WAWest Jul 2025target 2027
Solar project G1004, Franklin County
Solar
10.0 MWIn study Franklin, WAWest Nov 2023target 2025
Solar project G0957, Benton County
Solar
10.0 MWIn study Benton, WAWest Oct 2023target 2027
Solar project 85, Adams County
Solar
5.0 MWIn study Adams, WAWest Apr 2019target 2020
Solar + storage project 84, Stevens County
Solar + storage
5.0 MWIn study Stevens, WAWest Apr 2019target 2024
Other project hist_q71, Stevens County
Other
4.5 MWPaused / redesign Stevens, WAWest
Solar project G1003, Adams County
Solar
3.0 MWIn study Adams, WAWest Nov 2023target 2025
Battery storage project 70, Spokane County
Battery storage
2.5 MWIn study Spokane, WAWest Aug 2018target 2019
Solar project G0943, Snohomish County
Solar
1.0 MWIn study Snohomish, WAWest Oct 2023target 2024
Solar + storage project 120, Spokane County
Solar + storage
1.0 MWIn study Spokane, WAWest Aug 2021target 2022
Solar project G1068, Clark County
Solar
1.0 MWIn study Clark, WAWest Jun 2024target 2024
Solar project G0968, Clark County
Solar
1.0 MWIn study Clark, WAWest Oct 2023target 2023
Solar project 71, Lincoln County
Solar
1.0 MWIn study Lincoln, WAWest Oct 2018target 2020
Other project 15, Skagit County
Other
0.8 MWIn study Skagit, WAWest Mar 2008target 2008
Gas project 41, Lincoln County
Gas
0.3 MWIn study Lincoln, WAWest Apr 2014target 2014
Page 4 of 4

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20122025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)