| Project | Capacity | Status |
|---|---|---|
| Coal project GI-0111a, Mcpherson County Coal |
750 MW | Withdrawn / abandoned |
| Solar + storage project G0926, Benton County Solar + storage |
750 MW | Withdrawn / abandoned |
| Coal project 106, Elmore County Coal |
750 MW | Withdrawn / abandoned |
| Coal project GI-2003-5, Morgan County Coal |
750 MW | Withdrawn / abandoned |
| Solar + storage project G0928, Benton County Solar + storage |
750 MW | Withdrawn / abandoned |
| Solar + storage project GI-2023-17, Crowley County Solar + storage |
750 MW | Withdrawn / abandoned |
| Solar + storage project Q403, Navajo County Solar + storage |
750 MW | Withdrawn / abandoned |
| Other project 524, Elmore County Other |
750 MW | Withdrawn / abandoned |
| Coal project 109, Elmore County Coal |
750 MW | Withdrawn / abandoned |
| Solar + storage project G0927, Benton County Solar + storage |
750 MW | Withdrawn / abandoned |
| Coal project GI-0111, Mcintosh County Coal |
750 MW | Withdrawn / abandoned |
| Other project 2013-G4 Other |
750 MW | Withdrawn / abandoned |
| Solar + storage project 2018-G2 Solar + storage |
750 MW | Withdrawn / abandoned |
| Gas project IA-PNM-2025-17, San Juan County Gas |
727 MW | Withdrawn / abandoned |
| Coal project 146, Jerome County Coal |
725 MW | Withdrawn / abandoned |
| Solar + storage project Q01, Maricopa County Solar + storage |
720 MW | Withdrawn / abandoned |
| Coal project Q1, San Juan County Coal |
700 MW | Withdrawn / abandoned |
| Onshore wind project Q03 Onshore wind |
700 MW | Withdrawn / abandoned |
| Coal project 14, Yellowstone County Coal |
700 MW | Withdrawn / abandoned |
| Coal project GI-0517, Campbell County Coal |
700 MW | Withdrawn / abandoned |
| Other project Q433, Coconino County Other |
700 MW | Withdrawn / abandoned |
| Onshore wind project G0251, Klickitat County Onshore wind |
700 MW | Withdrawn / abandoned |
| 700MW Sickler-Schultz Gas · Calpine Energy Services, L.P. |
700 MW | Withdrawn / abandoned |
| Solar project Q17, Maricopa County Solar |
700 MW | Withdrawn / abandoned |
| Other project Q551, Coconino County Other |
700 MW | Withdrawn / abandoned |
| Coal project GI-0702, Campbell County Coal |
700 MW | Withdrawn / abandoned |
| Coal project GI-0610, Stanley County Coal |
700 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-5, Baca County Onshore wind |
700 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-4, Baca County Onshore wind |
700 MW | Withdrawn / abandoned |
| Other project Q512, Mohave County Other |
700 MW | Withdrawn / abandoned |
| Onshore wind project GI-2020-14, Cheyenne County Onshore wind |
700 MW | Withdrawn / abandoned |
| Onshore wind project IA-PNM-2019-06, Torrance County Onshore wind |
700 MW | Withdrawn / abandoned |
| Solar + storage project Q43, Navajo County Solar + storage |
700 MW | Withdrawn / abandoned |
| Coal project GI-2007-1, Morgan County Coal |
675 MW | Withdrawn / abandoned |
| Coal project GI-2007-2, Bent County Coal |
675 MW | Withdrawn / abandoned |
| Gas project GI-2008-1, Denver County Gas |
675 MW | Withdrawn / abandoned |
| Onshore wind project GI-0804, Logan County Onshore wind |
672 MW | Withdrawn / abandoned |
| Onshore wind project 1153, Carbon County Onshore wind |
665 MW | Withdrawn / abandoned |
| Onshore wind project Q281, Navajo County Onshore wind |
665 MW | Withdrawn / abandoned |
| Solar + storage project G1000, Morrow County Solar + storage |
660 MW | Withdrawn / abandoned |
| Solar + storage project Q506, Maricopa County Solar + storage |
660 MW | Withdrawn / abandoned |
| Gas project Q04, Pinal County Gas |
659 MW | Withdrawn / abandoned |
| Gas project 213, Elmore County Gas |
650 MW | Withdrawn / abandoned |
| Gas project 242, Payette County Gas |
650 MW | Withdrawn / abandoned |
| Gas project 217, Elmore County Gas |
650 MW | Withdrawn / abandoned |
| Gas project 261, Payette County Gas |
650 MW | Withdrawn / abandoned |
| Battery storage project G0798, Wasco County Battery storage |
650 MW | Withdrawn / abandoned |
| Battery storage project G0952, Gilliam County Battery storage |
650 MW | Withdrawn / abandoned |
| Battery storage project G0951, Gilliam County Battery storage |
650 MW | Withdrawn / abandoned |
| Gas project 246, Payette County Gas |
650 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)