πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

GAS Β· WEST

700MW Sickler-Schultz

700MW Sickler-Schultz is a 700 MW gas request withdrawn in the West interconnection queue, in Benton County, Washington, connecting to Calpine Energy Services, L.P..

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2001 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G59
Grid region
West (non-ISO utilities)
Utility / transmission owner
Calpine Energy Services, L.P.
Developer
Calpine Energy Services, L.P.
Connection point (POI)
Sickler-Schultz 500 kV
Location
Benton County, Washington
Technology
Gas: 700 MW
Total requested
700 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
31 May 2001
Proposed online date
June 2005

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem