United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in West (non-ISO utilities) — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown34960.6 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

349 requests · page 4 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 639, Ada County
Battery storage · Idaho Power Company‚ÄîPower Supply
150 MWAgreement signed Ada, IDWest Feb 2022target 2026
Sf150SB
Solar + storage
150 MWAgreement signed El Paso, TXWest Mar 2024target 2027
Solar + storage project IA-PNM-2021-09, Bernalillo County
Solar + storage · NextEra Energy
150 MWAgreement signed Bernalillo, NMWest Jul 2021target 2025
Corazon Energy Storage
Battery storage
150 MWAgreement signed Bernalillo, NMWest Jul 2021target 2024
Battery storage project IA-PNM-2021-16, Sandoval County
Battery storage · EsVolta Development
150 MWAgreement signed Sandoval, NMWest Jul 2021target 2024
Battery storage project Q299, Maricopa County
Battery storage
150 MWAgreement signed Maricopa, AZWest Mar 2019target 2023
Solar project Company IG, Humboldt County
Solar
150 MWAgreement signed Humboldt, NVWest Mar 2018target 2023
Solar + storage project GI-DISIS-2021-04, Otero County
Solar + storage
150 MWAgreement signed Otero, NMWest May 2021target 2028
Globemallow Solar
Solar + storage
150 MWAgreement signed Santa Fe, NMWest Jul 2021target 2024
Battery storage project IA-PNM-2019-19, Bernalillo County
Battery storage · PNM ‚Äì Generation
150 MWAgreement signed Bernalillo, NMWest Apr 2019target 2021
Battery storage project IA-PNM-2020-17, Bernalillo County
Battery storage · AES Renewable Holdings
150 MWAgreement signed Bernalillo, NMWest Sep 2020target 2023
Onshore wind project GI-TC-2024-08, Kit Carson County
Onshore wind
150 MWAgreement signed Kit Carson, COWest May 2023target 2027
Solar + storage project Company 168, Clark County
Solar + storage
150 MWAgreement signed Clark, NVWest Sep 2018target 2026
Solar project 636, Elmore County
Solar · Soles Rest Solar LLC
149 MWAgreement signed Elmore, IDWest Feb 2022target 2028
Onshore wind project IA-PNM-2020-01, Guadalupe County
Onshore wind
145 MWAgreement signed Guadalupe, NMWest Jan 2020target 2021
Solar project GI-TC-2021-01, Moffat County
Solar
145 MWAgreement signed Moffat, COWest Mar 2021target 2024
NMRD Data Center IV
Solar
140 MWAgreement signed Sandoval, NMWest Jan 2017target 2022
Solar + storage project 5, Grant County
Solar + storage
130 MWAgreement signed Grant, WAWest Jul 2020
Solar + storage project Q264, Pinal County
Solar + storage
130 MWAgreement signed Pinal, AZWest Sep 2017target 2021
Battery storage project 112, Thurston County
Battery storage
127 MWAgreement signed Thurston, WAWest Jun 2021target 2029
Solar project 588, Ada County
Solar · PVS 2, LLC
125 MWAgreement signed Ada, IDWest Sep 2020target 2026
Battery storage project Company JP, Washoe County
Battery storage
125 MWAgreement signed Washoe, NVWest Sep 2018target 2027
Solar + storage project Company JE, Churchill County
Solar + storage
125 MWAgreement signed Churchill, NVWest Sep 2018target 2027
Solar project 558, Jerome County
Solar · Cat Creek Energy, LLC
120 MWAgreement signed Jerome, IDWest May 2019target 2026
Onshore wind project 715, Uinta County
Onshore wind · Uinta Wind Energy, LLC
120 MWAgreement signed Uinta, WYWest Oct 2015target 2025
AC120SB Project
Solar + storage
120 MWAgreement signed Otero, NMWest Sep 2017target 2022
Solar project Company IA, Washoe County
Solar
120 MWAgreement signed Washoe, NVWest Dec 2017target 2024
Solar project GI-2010-19, Pueblo County
Solar
120 MWAgreement signed Pueblo, COWest Nov 20102016
Solar + storage project 1, Grant County
Solar + storage
120 MWAgreement signed Grant, WAWest Sep 2017
Solar project GI-2014-9, Pueblo County
Solar
120 MWAgreement signed Pueblo, COWest Oct 2014target 2016
Geothermal project Company LB, Pershing County
Geothermal
115 MWAgreement signed Pershing, NVWest Mar 2021target 2029
Gas project GI-2006-1a, Jefferson County
Gas
115 MWAgreement signed Jefferson, COWest Jan 2006target 2007
Gas project CLPT G22, Laramie County
Gas · Black Hills Electric Generation, LLC
115 MWAgreement signed Laramie, WYWest Nov 2022target 2024
Solar project GI-TC-2021-03, Dolores County
Solar
110 MWAgreement signed Dolores, COWest Mar 2021target 2024
Solar project BHBE G23, Oglala Lakota County
Solar
110 MWAgreement signed Oglala Lakota, SDWest Nov 2022target 2026
Onshore wind project 13, Kittitas County
Onshore wind
104 MWAgreement signed Kittitas, WAWest Sep 2007target 2008
Onshore wind project GI-1401, Butte County
Onshore wind
103 MWAgreement signed Butte, SDWest Jan 2014
Solar project 734, Crook County
Solar · Aurora Solar, LLC
102 MWAgreement signed Crook, ORWest Mar 2016target 2025
Battery storage project GI-TC-2024-19, Montrose County
Battery storage
100 MWAgreement signed Montrose, COWest May 2024target 2027
CO100SB Project
Solar + storage
100 MWAgreement signed Otero, NMWest Mar 2019target 2027
Ne100B
Battery storage
100 MWAgreement signed El Paso, TXWest Mar 2024target 2027
Solar + storage project 604, Elmore County
Solar + storage · Crimson Orchard Solar LLC
100 MWAgreement signed Elmore, IDWest May 2021target 2026
Solar + storage project 732, Baker County
Solar + storage · MN8 Energy Development Company LLC
100 MWAgreement signed Baker, ORWest Aug 2023target 2029
Onshore wind project 786, Summit County
Onshore wind · Echo Divide Wind, LLC
100 MWAgreement signed Summit, UTWest Aug 2016target 2027
Solar + storage project 719, Blaine County
Solar + storage · Moonstone Energy 2, LLC
100 MWAgreement signed Blaine, IDWest Jun 2023target 2028
Battery storage project 86, Whatcom County
Battery storage
100 MWAgreement signed Whatcom, WAWest Jul 2020target 2030
Solar project Company 140, Clark County
Solar
100 MWAgreement signed Clark, NVWest Sep 2014target 2025
SS100S
Solar
100 MWAgreement signed El Paso, TXWest Sep 2022target 2025
Solar + storage project Company 174, Clark County
Solar + storage
100 MWAgreement signed Clark, NVWest Mar 2019target 2023
Coal project BHBE G2, Campbell County
Coal · Black Hills Generation
100 MWAgreement signed Campbell, SDWest Feb 2001target 2010

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)