United States › Grid › Interconnection queues › Colorado
SOLAR · WESTSolar project GI-TC-2021-03, Dolores County
Solar project GI-TC-2021-03, Dolores County is a 110 MW solar request with a signed interconnection agreement in the West interconnection queue, in Dolores County, Colorado, connecting to Tri-State Generation and Transmission Association.
Queue statusConsented
- PlanningQueued Mar 2021 (completed)
- ConsentedJun 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GI-TC-2021-03
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Tri-State Generation and Transmission Association
- Connection point (POI)
- Cahone 115kV Substation
- Location
- Dolores County, Colorado
- Technology
- Solar: 110 MW
- Total requested
- 110 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed LGIA
- Queue status
- Active
- Entered queue
- 15 March 2021
- Agreement signed
- 14 June 2024
- Proposed online date
- June 2024
Location
Marker shows the centre of Dolores County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem