Withdrawn queue requests in the USA (2021 requests) — page 34

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,149339.1 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,149 requests · page 34 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH1-161, Mercer County
Solar
20.0 MWWithdrawn / abandoned Mercer, PAPJM Aug 2021target 2023
Solar + storage project AH1-095, Huron County
Solar + storage
20.0 MWWithdrawn / abandoned Huron, OHPJM Jul 2021target 2025
Solar project AG2-278, Fayette County
Solar
20.0 MWWithdrawn / abandoned Fayette, OHPJM Mar 2021target 2023
Solar project AG2-143, Clarion County
Solar · CP McCall Road LLC
20.0 MWWithdrawn / abandoned Clarion, PAPJM Feb 2021target 2026
Solar project LGE-GIS-2021-022, Wise County
Solar
20.0 MWWithdrawn / abandoned Wise, VASoutheast Sep 2021target 2023
Solar project AH1-407, Northumberland County
Solar
20.0 MWWithdrawn / abandoned Northumberland, PAPJM Sep 2021target 2024
Solar project AG2-668, Clearfield County
Solar · Du Bois PV I, LLC
20.0 MWWithdrawn / abandoned Clearfield, PAPJM Mar 2021target 2023
Solar project AH1-379, Pulaski County
Solar
20.0 MWWithdrawn / abandoned Pulaski, VAPJM Sep 2021target 2024
Solar project AH1-573, Marion County
Solar · Swamp Fox Solar, LLC
20.0 MWWithdrawn / abandoned Marion, OHPJM Sep 2021target 2024
White Springs Solar
Solar · ACE DevCo NC
20.0 MWWithdrawn / abandoned Ontario, NYNYISO Oct 2021
ASD Carmen PA2 Solar
Solar · ASD Carmen PA2 Solar LLC
20.0 MWWithdrawn / abandoned Crawford, PAPJM Aug 2021target 2023
Solar project AH2-016, Somerset County
Solar
20.0 MWWithdrawn / abandoned Somerset, PAPJM Oct 2021target 2023
74972 Cicero
Solar · Nexamp Solar
20.0 MWWithdrawn / abandoned Oneida, NYNYISO Jul 2021
47763 Cayuta
Solar · Nexamp Solar
20.0 MWWithdrawn / abandoned Schuyler, NYNYISO Aug 2021
Solar project AH1-185, Isle Of Wight County
Solar · Prairie Solar, LLC
20.0 MWWithdrawn / abandoned Isle Of Wight, VAPJM Aug 2021target 2022
Solar project AH1-169, Accomack County
Solar
20.0 MWWithdrawn / abandoned Accomack, VAPJM Aug 2021target 2024
Solar + storage project AH1-382, Mercer County
Solar + storage
20.0 MWWithdrawn / abandoned Mercer, KYPJM Sep 2021target 2025
Solar project AH2-004, Halifax County
Solar
20.0 MWWithdrawn / abandoned Halifax, VAPJM Oct 2021target 2024
Solar project AG2-147, Livingston County
Solar
20.0 MWWithdrawn / abandoned Livingston, ILPJM Feb 2021target 2024
Solar project AH1-010, Grant County
Solar
20.0 MWWithdrawn / abandoned Grant, WVPJM Apr 2021target 2023
Solar project AG2-079, Bedford County
Solar
20.0 MWWithdrawn / abandoned Bedford, PAPJM Jan 2021target 2022
Battery storage project J2012, Tangipahoa Parish County
Battery storage
20.0 MWWithdrawn / abandoned Tangipahoa Parish, LAMISO Nov 2021target 2025
26338 Westmoreland
Solar · Nexamp Solar
20.0 MWWithdrawn / abandoned Oneida, NYNYISO Jul 2021
Solar project AH1-389, Warren County
Solar
20.0 MWWithdrawn / abandoned Warren, OHPJM Sep 2021target 2023
Solar project LGE-GIS-2021-026, Wise County
Solar
20.0 MWWithdrawn / abandoned Wise, VASoutheast Oct 2021target 2023
Battery storage project AG2-381, Caroline County
Battery storage
20.0 MWWithdrawn / abandoned Caroline, MDPJM Mar 2021target 2023
ELP Claverack Solar II LLC
Solar + storage · ELP Claverack Solar II LLC
20.0 MWWithdrawn / abandoned Columbia, NYNYISO Sep 2021
Allegany 2 Battery 2
Battery storage · Northland Power U.S. Projects
20.0 MWWithdrawn / abandoned Allegany, NYNYISO Jan 2021
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Addison, VTISO-NE Apr 2021target 2022
Solar project AG2-652, Carbon County
Solar
20.0 MWWithdrawn / abandoned Carbon, PAPJM Mar 2021target 2024
Solar project AH1-230, Tioga County
Solar
20.0 MWWithdrawn / abandoned Tioga, PAPJM Sep 2021target 2025
Solar
Solar
20.0 MWWithdrawn / abandoned Coos, NHISO-NE Sep 2021target 2023
Solar project AH1-062, Madison County
Solar
20.0 MWWithdrawn / abandoned Madison, OHPJM Jul 2021target 2024
Solar project AH1-576, Kent County
Solar
20.0 MWWithdrawn / abandoned Kent, DEPJM Sep 2021target 2024
Solar project AH1-353, Stephenson County
Solar · Blue Violet Energy, LLC
20.0 MWWithdrawn / abandoned Stephenson, ILPJM Sep 2021target 2024
Battery storage project AH1-129, Pittsylvania County
Battery storage
20.0 MWWithdrawn / abandoned Pittsylvania, VAPJM Aug 2021target 2023
Solar project AH2-005, Prince Edward County
Solar
20.0 MWWithdrawn / abandoned Prince Edward, VAPJM Oct 2021target 2024
Solar project AG2-594, Columbia County
Solar · North Corners Energy, LLC
20.0 MWWithdrawn / abandoned Columbia, PAPJM Mar 2021target 2024
Solar + storage project AG2-593, Columbia County
Solar + storage
20.0 MWWithdrawn / abandoned Columbia, PAPJM Mar 2021target 2024
Battery storage project AH1-064, City Of Hopewell County
Battery storage
20.0 MWWithdrawn / abandoned City Of Hopewell, VAPJM Jul 2021target 2023
Battery storage project AG2-202, City Of Lynchburg County
Battery storage · James Energy Center, LLC
20.0 MWWithdrawn / abandoned City Of Lynchburg, VAPJM Mar 2021target 2022
Bluepoint Grid
Battery storage · Bluepoint Grid, LLC
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jun 2021
Battery storage project AG2-653, Carbon County
Battery storage
20.0 MWWithdrawn / abandoned Carbon, PAPJM Mar 2021target 2024
Solar + storage project AG2-103, Accomack County
Solar + storage
20.0 MWWithdrawn / abandoned Accomack, VAPJM Jan 2021target 2024
Solar project AH2-003, Halifax County
Solar
20.0 MWWithdrawn / abandoned Halifax, VAPJM Oct 2021target 2024
West River Solar
Solar · West River Solar
20.0 MWWithdrawn / abandoned Saratoga, NYNYISO May 2021
Garnett Battery Storage
Battery storage · Garnet Energy Center, LLC,
20.0 MWWithdrawn / abandoned Cayuga, NYNYISO Apr 2021
Solar project AH1-118, Brooke County
Solar
20.0 MWWithdrawn / abandoned Brooke, WVPJM Aug 2021target 2023
Solar project AG2-243, Ashtabula County
Solar
20.0 MWWithdrawn / abandoned Ashtabula, OHPJM Mar 2021target 2023
Solar project G0690, Jefferson County
Solar
20.0 MWWithdrawn / abandoned Jefferson, ORWest Sep 2021target 2022
Page 34 of 43

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)