| Project | Capacity | Status |
|---|---|---|
| Onshore wind project GI-56, Sullivan County Onshore wind |
77.5 MW | Withdrawn / abandoned |
| Solar + storage project IC-902, Emanuel County Solar + storage |
76.0 MW | Withdrawn / abandoned |
| Solar project IC-521, Washington County Solar |
76.0 MW | Withdrawn / abandoned |
| Solar project 22136, Florence County Solar |
75.5 MW | Withdrawn / abandoned |
| Solar + storage project LGE-GIS-2024-001, Grayson County Solar + storage |
75.0 MW | Withdrawn / abandoned |
| Solar project 255, Saluda County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 56, Berkeley County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 94, Horry County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 917547, Greenwood County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project IC-480, Escambia County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar + storage project 425C, Leon County Solar + storage · Third Party |
75.0 MW | Withdrawn / abandoned |
| Solar project 70688, Greenwood County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project IC-674, Brooks County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 108, Orangeburg County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 249, Clarendon County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 280, Jackson County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 243, Florence County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 93, Georgetown County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 569088, Anderson County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 20853, Beaufort County Solar · Masked |
75.0 MW | Withdrawn / abandoned |
| Solar project 201, Alachua County Solar · Masked |
75.0 MW | Withdrawn / abandoned |
| Solar + storage project 425D, Leon County Solar + storage · Third Party |
75.0 MW | Withdrawn / abandoned |
| Solar project 61, Dillon County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 916493, Kershaw County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 265, Saluda County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar + storage project 458B, Jackson County Solar + storage · Third Party |
75.0 MW | Withdrawn / abandoned |
| Solar project IC-559, Clay County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 189, Williamsburg County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 42, Clarendon County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar + storage project 458A, Jackson County Solar + storage · Third Party |
75.0 MW | Withdrawn / abandoned |
| Solar project 110, Orangeburg County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 133, Dorchester County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 20230829015, Lexington County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 82, Aiken County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 256, Orangeburg County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 248, Williamsburg County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project IC-474, Perry County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project IC-378, Taylor County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar + storage project 204, Sumter County Solar + storage |
75.0 MW | Withdrawn / abandoned |
| Solar project 220662, Anderson County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 57, Williamsburg County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 533, Overton County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 890907, Montgomery County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 921117, Wilson County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project IC-517, Lee County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 136, Georgetown County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 284, Carroll County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-953, Perry County Solar + storage |
75.0 MW | Withdrawn / abandoned |
| Solar project 58, Barnwell County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 663, Henry County Solar |
75.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)