United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

SOLAR + STORAGE Β· SOUTHEAST

Solar + storage project 425C, Leon County

Solar + storage project 425C, Leon County is a 75.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Leon County, Florida, connecting to Florida Power & Light.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
425C
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
Third Party
Connection point (POI)
Raven - Sinai 161kV line
Location
Leon County, Florida
Technology
Solar: 75.0 MW Β· Battery
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
19 February 2022
Proposed online date
December 2024

Location

Marker shows the centre of Leon County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in Leon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem