United States βΊ Grid βΊ Interconnection queues βΊ Tennessee
SOLAR Β· SOUTHEASTSolar project 533, Overton County
Solar project 533, Overton County is a 75.0 MW solar request withdrawn in the Southeast interconnection queue, in Overton County, Tennessee, connecting to Tennessee Valley Authority.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 533
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Location
- Overton County, Tennessee
- Technology
- Solar: 75.0 MW
- Total requested
- 75.0 MW
- Queue status
- Withdrawn
- Entered queue
- 22 March 2023
- Proposed online date
- August 2028
Location
Marker shows the centre of Overton County; the queue data does not give exact sites.
Power plants in Tennessee Β· Transmission lines in Tennessee
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem