United States › Grid › Interconnection queues › Kansas

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Kansas — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown38780.4 GW
Active in queue32.6 GW140 requests
Agreement signed9,162 MW47 requests
Withdrawn38780.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

387 requests · page 3 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2022-206, Edwards County
Onshore wind
250 MWWithdrawn / abandoned Edwards, KSSPP Mar 2023target 2027
Onshore wind project GEN-2024-197, Edwards County
Onshore wind
250 MWWithdrawn / abandoned Edwards, KSSPP Mar 2025target 2028
Onshore wind project GEN-2022-094, Osborne County
Onshore wind
250 MWWithdrawn / abandoned Osborne, KSSPP Nov 2022target 2028
Solar project GEN-2023-122, Coffey County
Solar
250 MWWithdrawn / abandoned Coffey, KSSPP Oct 2023target 2030
Onshore wind project GEN-2023-093, Morton County
Onshore wind
250 MWWithdrawn / abandoned Morton, KSSPP Oct 2023target 2030
Onshore wind project GEN-2023-139, Osborne County
Onshore wind
250 MWWithdrawn / abandoned Osborne, KSSPP Oct 2023target 2028
Onshore wind project GEN-2023-068, Stanton County
Onshore wind
250 MWWithdrawn / abandoned Stanton, KSSPP Oct 2023target 2030
Onshore wind project GEN-2023-089, Finney County
Onshore wind
250 MWWithdrawn / abandoned Finney, KSSPP Oct 2023target 2028
Onshore wind project GEN-2023-141, Osborne County
Onshore wind
225 MWWithdrawn / abandoned Osborne, KSSPP Oct 2023target 2028
Onshore wind project GEN-2022-096, Osborne County
Onshore wind
225 MWWithdrawn / abandoned Osborne, KSSPP Nov 2022target 2028
Solar project GEN-2023-194, Cherokee County
Solar
225 MWWithdrawn / abandoned Cherokee, KSSPP Oct 2023target 2028
Battery storage project GEN-2023-215, Pratt County
Battery storage
225 MWWithdrawn / abandoned Pratt, KSSPP Oct 2023target 2027
Onshore wind project GEN-2016-122, Ellsworth County
Onshore wind
225 MWWithdrawn / abandoned Ellsworth, KSSPP Nov 20162020
Onshore wind project GEN-2017-179, Sedgwick County
Onshore wind
222 MWWithdrawn / abandoned Sedgwick, KSSPP Nov 2017target 2026
Onshore wind project GEN-2024-101, Finney County
Onshore wind
220 MWWithdrawn / abandoned Finney, KSSPP Mar 2025target 2031
Gas project GEN-2012-042, Ford County
Gas
220 MWWithdrawn / abandoned Ford, KSSPP Sep 2012target 2014
Onshore wind project GEN-2016-112, Ellsworth County
Onshore wind
220 MWWithdrawn / abandoned Ellsworth, KSSPP Nov 20162020
Onshore wind project GEN-2016-073, Kingman County
Onshore wind
220 MWWithdrawn / abandoned Kingman, KSSPP Mar 20162025
Battery storage project GEN-2022-081, Washington County
Battery storage
218 MWWithdrawn / abandoned Washington, KSSPP Sep 2022target 2027
Onshore wind project GEN-2017-130, Osage County
Onshore wind
215 MWWithdrawn / abandoned Osage, KSSPP Nov 2017target 2020
Solar project GEN-2017-204, Mcpherson County
Solar
210 MWWithdrawn / abandoned Mcpherson, KSSPP Nov 2017target 2020
Onshore wind project GEN-2006-006, Ford County
Onshore wind
206 MWWithdrawn / abandoned Ford, KSSPP Feb 2006target 2008
Onshore wind project GEN-2007-047, Thomas County
Onshore wind
204 MWWithdrawn / abandoned Thomas, KSSPP Oct 2007target 2009
Onshore wind project GEN-2017-063, Rush County
Onshore wind
202 MWWithdrawn / abandoned Rush, KSSPP May 2017target 2019
Onshore wind project GEN-2017-128, Jackson County
Onshore wind
202 MWWithdrawn / abandoned Jackson, KSSPP Nov 2017target 2026
Onshore wind project GEN-2007-058, Stevens County
Onshore wind
202 MWWithdrawn / abandoned Stevens, KSSPP Dec 2007target 2011
Onshore wind project GEN-2007-059, Stevens County
Onshore wind
202 MWWithdrawn / abandoned Stevens, KSSPP Dec 2007target 2012
Solar project GEN-2017-191, Osage County
Solar
202 MWWithdrawn / abandoned Osage, KSSPP Nov 20172025
Solar project GEN-2017-193, Shawnee County
Solar
202 MWWithdrawn / abandoned Shawnee, KSSPP Nov 2017target 2020
Onshore wind project GEN-2004-011, Anderson County
Onshore wind
201 MWWithdrawn / abandoned Anderson, KSSPP Apr 2004target 2006
Onshore wind project GEN-2007-022, Anderson County
Onshore wind
201 MWWithdrawn / abandoned Anderson, KSSPP May 2007target 2009
Onshore wind project GEN-2011-059, Ford County
Onshore wind
201 MWWithdrawn / abandoned Ford, KSSPP Oct 2011target 2015
Onshore wind project GEN-2005-001, Anderson County
Onshore wind
201 MWWithdrawn / abandoned Anderson, KSSPP Jan 2005target 2006
Onshore wind project GEN-2003-024, Morris County
Onshore wind
201 MWWithdrawn / abandoned Morris, KSSPP Dec 2003target 2005
Onshore wind project GEN-2005-014, Anderson County
Onshore wind
201 MWWithdrawn / abandoned Anderson, KSSPP Aug 2005target 2007
Onshore wind project GEN-2004-024, Elk County
Onshore wind
201 MWWithdrawn / abandoned Elk, KSSPP Dec 2004target 2006
Onshore wind project GEN-2011-016, Hodgeman County
Onshore wind
200 MWWithdrawn / abandoned Hodgeman, KSSPP Mar 20112017
Onshore wind project GEN-2010-015, Hodgeman County
Onshore wind
200 MWWithdrawn / abandoned Hodgeman, KSSPP Mar 2010target 2013
Onshore wind project GEN-2013-020, Marion County
Onshore wind
200 MWWithdrawn / abandoned Marion, KSSPP Jun 2013target 2014
Onshore wind project GEN-2008-127, Sumner County
Onshore wind
200 MWWithdrawn / abandoned Sumner, KSSPP Dec 2008target 2011
Onshore wind project GEN-2009-005, Lyon County
Onshore wind
200 MWWithdrawn / abandoned Lyon, KSSPP Feb 2009target 2010
Solar project GEN-2022-025, Decatur County
Solar
200 MWWithdrawn / abandoned Decatur, KSSPP Jun 20222025
Onshore wind project GEN-2007-036, Ford County
Onshore wind
200 MWWithdrawn / abandoned Ford, KSSPP Sep 2007target 2012
Onshore wind project GEN-2017-030, Ford County
Onshore wind
200 MWWithdrawn / abandoned Ford, KSSPP May 2017target 2020
Onshore wind project GEN-2022-193, Ford County
Onshore wind
200 MWWithdrawn / abandoned Ford, KSSPP Feb 2023target 2027
Onshore wind project GEN-2004-002, Elk County
Onshore wind
200 MWWithdrawn / abandoned Elk, KSSPP Jan 2004target 2005
Onshore wind project GEN-2016-012, Anderson County
Onshore wind
200 MWWithdrawn / abandoned Anderson, KSSPP Mar 2016target 2018
Battery storage project GEN-2023-023, Wyandotte County
Battery storage
200 MWWithdrawn / abandoned Wyandotte, KSSPP Oct 2023target 2028
Solar project GEN-2022-158, Rush County
Solar
200 MWWithdrawn / abandoned Rush, KSSPP Feb 2023target 2028
Onshore wind project GEN-2017-185, Sumner County
Onshore wind
200 MWWithdrawn / abandoned Sumner, KSSPP Nov 20172020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)