Solar project GEN-2022-158, Rush County

Solar project GEN-2022-158, Rush County is a 200 MW solar request withdrawn in the SPP interconnection queue, in Rush County, Kansas, connecting to ITCGP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-158
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
ITCGP
Connection point (POI)
Spearville - Postrock 345kV Substation
Location
Rush County, Kansas
Technology
Solar: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
24 February 2023
Proposed online date
December 2028
Withdrawn
November 2023

Location

Marker shows the centre of Rush County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Rush County