SOLAR Β· SPPSolar project GEN-2022-158, Rush County
Solar project GEN-2022-158, Rush County is a 200 MW solar request withdrawn in the SPP interconnection queue, in Rush County, Kansas, connecting to ITCGP.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2023 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-158
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- ITCGP
- Connection point (POI)
- Spearville - Postrock 345kV Substation
- Location
- Rush County, Kansas
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 24 February 2023
- Proposed online date
- December 2028
- Withdrawn
- November 2023
Location
Marker shows the centre of Rush County; the queue data does not give exact sites.
Other requests in Rush County
- Solar project GEN-2024-085, Rush CountySolar Β· 160 MW Β· in study
- Onshore wind project GEN-2009-020, Rush CountyOnshore wind Β· 48.3 MW Β· built
- Onshore wind project GEN-2014-025, Rush CountyOnshore wind Β· 2.4 MW Β· built
- Onshore wind project GEN-2016-049, Rush CountyOnshore wind Β· 310 MW Β· withdrawn
- Onshore wind project GEN-2017-063, Rush CountyOnshore wind Β· 202 MW Β· withdrawn
- Onshore wind project GEN-2014-072, Rush CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2010-016, Rush CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2009-051, Rush CountyOnshore wind Β· 102 MW Β· withdrawn
- Onshore wind project GEN-2009-052, Rush CountyOnshore wind Β· 102 MW Β· withdrawn
- Onshore wind project GEN-2009-026, Rush CountyOnshore wind Β· 102 MW Β· withdrawn
- Onshore wind project GEN-2009-043, Rush CountyOnshore wind Β· 102 MW Β· withdrawn
- Onshore wind project GEN-2013-041, Rush CountyOnshore wind Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem