Onshore wind project NC5-009, Mohave County Onshore wind |
300 MW | In study |
Mohave, AZ | West |
Apr 2022 | target 2027 |
Solar + storage project 124, Pinal County Solar + storage |
300 MW | In study |
Pinal, AZ | West |
Jun 2022 | target 2025 |
Other project CLPT G16, Platte County Other Β· NextEra Energy Resources Interconnection Holdings, LLC |
300 MW | Agreement signed |
Platte, WY | West |
Apr 2022 | target 2025 |
Solar + storage project Q443, Yuma County Solar + storage |
300 MW | In study |
Yuma, AZ | West |
Mar 2022 | target 2027 |
Solar + storage project Company NS, Eureka County Solar + storage |
300 MW | Paused / redesign |
Eureka, NV | West |
Sep 2022 | target 2029 |
Onshore wind project Company NA, White Pine County Onshore wind |
300 MW | Paused / redesign |
White Pine, NV | West |
Mar 2022 | target 2030 |
Onshore wind project 118, Apache County Onshore wind |
300 MW | In study |
Apache, AZ | West |
Apr 2022 | target 2025 |
Solar + storage project 656, Jerome County Solar + storage Β· Red Bridge Energy, LLC |
300 MW | Paused / redesign |
Jerome, ID | West |
May 2022 | target 2027 |
Solar + storage project Company MU, White Pine County Solar + storage |
300 MW | Paused / redesign |
White Pine, NV | West |
Mar 2022 | target 2030 |
Solar + storage project Company ND, Lander County Solar + storage |
300 MW | Paused / redesign |
Lander, NV | West |
Mar 2022 | target 2030 |
Wind + storage project IA-PNM-2023-08, Guadalupe County Wind + storage |
300 MW | In study |
Guadalupe, NM | West |
Dec 2022 | target 2025 |
Solar project 419, Big Horn County Solar |
300 MW | In study |
Big Horn, MT | West |
Feb 2022 | target 2025 |
Solar project BHBE G19, Campbell County Solar |
300 MW | Agreement signed |
Campbell, SD | West |
May 2022 | target 2024 |
Solar + storage project C2-82, Bannock County Solar + storage Β· BRP Garnet 1, LLC |
300 MW | Agreement signed |
Bannock, ID | West |
May 2022 | target 2027 |
Battery storage project Company 219, Clark County Battery storage |
300 MW | Paused / redesign |
Clark, NV | West |
Mar 2022 | target 2029 |
Solar + storage project GI-DISIS-2022-28, Kit Carson County Solar + storage |
299 MW | Paused / redesign |
Kit Carson, CO | West |
May 2022 | target 2029 |
Solar + storage project GI-DISIS-2022-45, Pueblo County Solar + storage |
299 MW | Paused / redesign |
Pueblo, CO | West |
May 2022 | target 2028 |
Solar + storage project GI-DISIS-2022-44, Moffat County Solar + storage |
299 MW | Paused / redesign |
Moffat, CO | West |
May 2022 | target 2030 |
Solar + storage project GI-DISIS-2022-02, Weld County Solar + storage |
299 MW | Agreement signed |
Weld, CO | West |
May 2022 | target 2030 |
Solar + storage project GI-DISIS-2022-07, Weld County Solar + storage |
299 MW | Agreement signed |
Weld, CO | West |
May 2022 | target 2029 |
Onshore wind project G0761, Grant County Onshore wind |
290 MW | In study |
Grant, WA | West |
Jun 2022 | target 2026 |
Battery storage project G0724, Curry County Battery storage |
280 MW | In study |
Curry, OR | West |
Jan 2022 | target 2026 |
Solar + storage project 26, Sacramento County Solar + storage |
275 MW | In study |
Sacramento, CA | West |
Sep 2022 | target 2030 |
Solar + storage project 119, Greenlee County Solar + storage |
270 MW | In study |
Greenlee, AZ | West |
Apr 2022 | target 2027 |
Solar + storage project GI-2022-162, Imperial County Solar + storage |
270 MW | In study |
Imperial, CA | West |
Sep 2022 | target 2026 |
Solar project CLPT G18, Converse County Solar Β· DUTC bn, LLC |
255 MW | Agreement signed |
Converse, WY | West |
Jun 2022 | target 2024 |
Solar + storage project Q475, Maricopa County Solar + storage |
250 MW | In study |
Maricopa, AZ | West |
Mar 2022 | target 2025 |
Solar project Company NR, Lassen County Solar |
250 MW | Agreement signed |
Lassen, CA | West |
Sep 2022 | target 2030 |
Onshore wind project IA-PNM-2023-01, Cibola County Onshore wind |
250 MW | In study |
Cibola, NM | West |
Oct 2022 | target 2025 |
Gas project 22-07251, Larimer County Gas |
250 MW | In study |
Larimer, CO | West |
Jul 2022 | target 2028 |
Solar + storage project 2022-G1, La Paz County Solar + storage |
250 MW | In study |
La Paz, AZ | West |
Jan 2022 | target 2025 |
Other project 112, Apache County Other |
250 MW | In study |
Apache, AZ | West |
Jan 2022 | target 2025 |
Battery storage project Company 217, Clark County Battery storage |
250 MW | Paused / redesign |
Clark, NV | West |
Mar 2022 | target 2029 |
Solar + storage project 2022-G7, Maricopa County Solar + storage |
250 MW | In study |
Maricopa, AZ | West |
Jun 2022 | target 2025 |
Solar + storage project Q446, Maricopa County Solar + storage |
250 MW | In study |
Maricopa, AZ | West |
Mar 2022 | target 2025 |
Solar project S0006, Carbon County Solar Β· PacifiCorp |
250 MW | In study |
Carbon, WY | West |
Mar 2022 | target 2026 |
Battery storage project Company NZ, Storey County Battery storage |
250 MW | Paused / redesign |
Storey, NV | West |
Sep 2022 | target 2030 |
Solar project BHBE G20, Dawes County Solar |
250 MW | Agreement signed |
Dawes, SD | West |
Jul 2022 | target 2025 |
Solar project S0005, Carbon County Solar Β· PacifiCorp |
250 MW | In study |
Carbon, WY | West |
Mar 2022 | target 2026 |
Onshore wind project Q458, Navajo County Onshore wind |
242 MW | In study |
Navajo, AZ | West |
Mar 2022 | target 2026 |
Solar project S0004, Carbon County Solar Β· PacifiCorp |
240 MW | In study |
Carbon, WY | West |
Mar 2022 | target 2026 |
Solar + storage project GI-DISIS-2022-04, Kit Carson County Solar + storage |
237 MW | Agreement signed |
Kit Carson, CO | West |
May 2022 | target 2027 |
Solar project S0003, Converse County Solar Β· PacifiCorp |
237 MW | In study |
Converse, WY | West |
Mar 2022 | target 2026 |
Solar + storage project 2022-G2, Mohave County Solar + storage |
225 MW | In study |
Mohave, AZ | West |
Apr 2022 | target 2025 |
Solar + storage project 2022-G5, Mohave County Solar + storage |
225 MW | In study |
Mohave, AZ | West |
Apr 2022 | target 2025 |
Solar + storage project GI-DISIS-2022-49, Prowers County Solar + storage |
225 MW | Paused / redesign |
Prowers, CO | West |
May 2022 | target 2029 |
Gas project Company 230, Clark County Gas |
222 MW | Agreement signed |
Clark, NV | West |
Sep 2022 | target 2024 |
Gas project Company 231, Clark County Gas |
222 MW | Agreement signed |
Clark, NV | West |
Sep 2022 | target 2024 |
Battery storage project Company 211, Clark County Battery storage |
220 MW | Agreement signed |
Clark, NV | West |
Jan 2022 | target 2029 |
Onshore wind project C2-92, Bingham County Onshore wind Β· PacifiCorp |
206 MW | In study |
Bingham, ID | West |
May 2022 | target 2026 |