πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Southeast (non-ISO utilities) (2022 requests) β€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown14217.0 GW
Active in queue17.0 GW142 requests
Agreement signed5,225 MW33 requests
Withdrawn21128.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

142 requests Β· page 3 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 446, St. Lucie County
Solar Β· FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2028
Solar project 456, Indian River County
Solar Β· FPL
74.5 MWIn study Indian River, FLSoutheast Apr 2022target 2031
Solar project 314, Levy County
Solar Β· Florida Renewable Partners, LLC
74.5 MWPaused / redesign Levy, FLSoutheast Aug 2022target 2026
Solar project 429, Desoto County
Solar Β· FPL
74.5 MWIn study Desoto, FLSoutheast Mar 2022target 2027
Solar project 489, Calhoun County
Solar Β· FPL
74.5 MWIn study Calhoun, FLSoutheast Aug 2022target 2026
Solar project 425B, Gadsden County
Solar Β· FPL
74.5 MWIn study Gadsden, FLSoutheast Feb 2022target 2033
Solar project 431, Hendry County
Solar Β· FPL
74.5 MWIn study Hendry, FLSoutheast Mar 2022target 2026
Solar project 458, St. Lucie County
Solar Β· FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 432, Indian River County
Solar Β· FPL
74.5 MWIn study Indian River, FLSoutheast Mar 2022target 2027
Solar project 476, Desoto County
Solar Β· FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2032
Solar project 478, Highlands County
Solar Β· FPL
74.5 MWIn study Highlands, FLSoutheast Jul 2022target 2029
Solar project 477, Desoto County
Solar Β· FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2030
Solar project 472, Desoto County
Solar Β· FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2029
Solar project 315, Levy County
Solar Β· Florida Renewable Partners, LLC
74.5 MWPaused / redesign Levy, FLSoutheast Aug 2022target 2026
Solar project 439, Desoto County
Solar Β· FPL
74.5 MWIn study Desoto, FLSoutheast Mar 2022target 2028
Solar project 452, Indian River County
Solar Β· FPL
74.5 MWIn study Indian River, FLSoutheast Apr 2022target 2029
Solar project 447, St. Lucie County
Solar Β· FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2027
Solar project 450, St. Lucie County
Solar Β· FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2030
Solar project 433, Manatee County
Solar Β· FPL
74.5 MWIn study Manatee, FLSoutheast Mar 2022target 2028
Solar project 464, Collier County
Solar Β· FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2028
Solar project 463, Collier County
Solar Β· FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2028
Solar project 445, St. Lucie County
Solar Β· FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2028
Solar project 312, Alachua County
Solar Β· Florida Renewable Partners, LLC
74.5 MWPaused / redesign Alachua, FLSoutheast Apr 2022target 2026
Solar project 428, Manatee County
Solar Β· FPL
74.5 MWIn study Manatee, FLSoutheast Mar 2022target 2026
Solar project 311, Alachua County
Solar Β· Florida Renewable Partners, LLC
74.5 MWPaused / redesign Alachua, FLSoutheast May 2022target 2025
Solar project 427, Indian River County
Solar Β· FPL
74.5 MWIn study Indian River, FLSoutheast Mar 2022target 2027
Solar project 474, Desoto County
Solar Β· FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2032
Solar project 955167, Johnston County
Solar
73.0 MWUnder construction Johnston, NCSoutheast Jun 2022target 2026
Solar project 572280, Greenwood County
Solar
72.0 MWAgreement signed Greenwood, SCSoutheast Jun 2022target 2028
Solar project 569164, Newberry County
Solar
70.7 MWIn study Newberry, SCSoutheast Jun 2022target 2027
Solar project 515, Haywood County
Solar
67.0 MWAgreement signed Haywood, TNSoutheast Aug 2022target 2025
Solar project 522, Choctaw County
Solar
67.0 MWIn study Choctaw, MSSoutheast Sep 2022target 2026
Solar + storage project IC-1103, Emanuel County
Solar + storage
64.0 MWAgreement signed Emanuel, GASoutheast Dec 2022target 2027
Solar project 566580, Lee County
Solar
60.0 MWUnder construction Lee, SCSoutheast Jun 2022target 2028
Battery storage project 566170, Wake County
Battery storage Β· Duke Energy Progress, LLC
56.0 MWAgreement signed Wake, NCSoutheast Jun 2022target 2026
Solar project 569804, Spartanburg County
Solar
54.0 MWAgreement signed Spartanburg, SCSoutheast Jun 2022target 2028
Solar project 519, Marshall County
Solar
50.0 MWAgreement signed Marshall, MSSoutheast Sep 2022target 2029
Solar project 569014, Kershaw County
Solar
48.0 MWAgreement signed Kershaw, SCSoutheast Jun 2022target 2028
Solar project 572354, Cherokee County
Solar
28.3 MWAgreement signed Cherokee, SCSoutheast Jun 2022target 2027
Hydro project 570430, Montgomery County
Hydro Β· Duke Energy Progress, LLC
6.3 MWUnder construction Montgomery, NCSoutheast Jun 2022target 2025
Battery storage project 561350, Fairfield County
Battery storage
4.6 MWUnder construction Fairfield, SCSoutheast Jun 2022target 2025
Battery storage project 563202, Burke County
Battery storage
2.7 MWUnder construction Burke, NCSoutheast Jun 2022target 2026
Page 3 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)