SOLAR + STORAGE · SOUTHEASTSolar + storage project IC-1103, Emanuel County
Solar + storage project IC-1103, Emanuel County is a 64.0 MW solar + storage request with a signed interconnection agreement in the Southeast interconnection queue, in Emanuel County, Georgia, connecting to Southern Company.
Queue statusConsented
- PlanningQueued Dec 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jul 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- IC-1103
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Vidalia - Wadley Primary (Black) 230 kV Line
- Location
- Emanuel County, Georgia
- Technology
- Solar: 64.0 MW · Battery
- Total requested
- 64.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- GIA Executed; NTP Pending
- Queue status
- Active
- Entered queue
- 22 December 2022
- Proposed online date
- July 2027
Location
Marker shows the centre of Emanuel County; the queue data does not give exact sites.
Other requests in Emanuel County
- Solar project IC-1097, Emanuel CountySolar · 200 MW · agreement signed
- Solar + storage project IC-1068, Emanuel CountySolar + storage · 124 MW · agreement signed
- Dellwood SolarSolar + storage · 150 MW · in study
- Solar + storage project IC-964, Emanuel CountySolar + storage · 150 MW · suspended
- Solar project IC-770, Emanuel CountySolar · 240 MW · withdrawn
- Solar project IC-776, Emanuel CountySolar · 125 MW · withdrawn
- Solar + storage project IC-902, Emanuel CountySolar + storage · 76.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem