| Project | Capacity | Status |
|---|---|---|
| Solar project AF1-310, Halifax County Solar |
300 MW | Withdrawn / abandoned |
| Battery storage project AH1-747, Warren County Battery storage · Cardinal Energy Storage East, LLC |
300 MW | Withdrawn / abandoned |
| Solar project AE2-031, Sussex County Solar |
290 MW | Withdrawn / abandoned |
| Solar project AE1-206, Hanover County Solar |
285 MW | Withdrawn / abandoned |
| Solar project AG2-635, Brunswick County Solar |
270 MW | Withdrawn / abandoned |
| Gas project G00_W40, Warren County Gas |
264 MW | Withdrawn / abandoned |
| Hydro project I09, Bath County Hydro |
252 MW | Withdrawn / abandoned |
| Solar project AD2-206, Greensville County Solar |
250 MW | Withdrawn / abandoned |
| Solar project AF1-329, Charles City County Solar |
250 MW | Withdrawn / abandoned |
| Other project 185, Washington County Other |
250 MW | Withdrawn / abandoned |
| Doswell Limited Partnership Battery storage · Doswell Limited Partnership |
250 MW | Withdrawn / abandoned |
| Battery storage project AG2-622, Hanover County Battery storage |
250 MW | Withdrawn / abandoned |
| Battery storage project AG2-350, Isle Of Wight County Battery storage |
250 MW | Withdrawn / abandoned |
| Solar project AC1-162, Prince Edward County Solar |
240 MW | Withdrawn / abandoned |
| Solar project AD2-193, Spotsylvania County Solar |
209 MW | Withdrawn / abandoned |
| Solar project AG2-680, Madison County Solar |
202 MW | Withdrawn / abandoned |
| Onshore wind project AC1-226, Pulaski County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar + storage project AE1-135, Greensville County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar project AG1-421, Augusta County Solar · Leeward Renewable Energy Development, LLC |
200 MW | Withdrawn / abandoned |
| Fitch Solar Solar |
200 MW | Withdrawn / abandoned |
| Gas project AF2-053, Charles City County Gas |
200 MW | Withdrawn / abandoned |
| Battery storage project AI1-010, Caroline County Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project AG1-143, Prince William County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project AE1-022, Fauquier County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project AH1-444, City Of Chesapeake County Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project AI1-032, Fauquier County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project AD2-190, Fauquier County Solar |
200 MW | Withdrawn / abandoned |
| Solar + storage project AI1-136, Brunswick County Solar + storage |
200 MW | Withdrawn / abandoned |
| Onshore wind project U2-071, Tazewell County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project AG1-432, Buckingham County Solar · ACE Development Company II, LLC |
200 MW | Withdrawn / abandoned |
| Solar project AG1-357, Lunenburg County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project AG2-646, Chesterfield County Battery storage · Pine Tree Power Management LLC |
200 MW | Withdrawn / abandoned |
| Battery storage project AG1-412, Caroline County Battery storage · Matta Grid, LLC |
200 MW | Withdrawn / abandoned |
| Solar + storage project AE2-260, Greensville County Solar + storage |
200 MW | Withdrawn / abandoned |
| Onshore wind project U2-017, Tazewell County Onshore wind |
200 MW | Withdrawn / abandoned |
| Battery storage project AH1-737, Goochland County Battery storage · Melrose Energy Center, LLC |
200 MW | Withdrawn / abandoned |
| Solar project AH1-465, Greensville County Solar |
200 MW | Withdrawn / abandoned |
| Solar + storage project AG2-597, Smyth County Solar + storage |
200 MW | Withdrawn / abandoned |
| Battery storage project AG1-534, Loudoun County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project AG1-235, City Of Chesapeake County Solar |
192 MW | Withdrawn / abandoned |
| Four Rivers NUG CC Gas |
190 MW | Withdrawn / abandoned |
| Keysville PV I, LLC Solar · Keysville PV I, LLC |
186 MW | Withdrawn / abandoned |
| Solar project AE1-235, Dinwiddie County Solar |
180 MW | Withdrawn / abandoned |
| Onshore wind project AD1-102, Pulaski County Onshore wind |
180 MW | Withdrawn / abandoned |
| Onshore wind project Z2-042, Pulaski County Onshore wind |
180 MW | Withdrawn / abandoned |
| Onshore wind project AC2-002, Pulaski County Onshore wind |
179 MW | Withdrawn / abandoned |
| Battery storage project AG1-184, Sussex County Battery storage · Cabin Point Solar, LLC |
175 MW | Withdrawn / abandoned |
| Solar project AG2-261, Greensville County Solar |
175 MW | Withdrawn / abandoned |
| Battery storage project AH2-226, Greensville County Battery storage |
175 MW | Withdrawn / abandoned |
| Solar + storage project AG2-428, Sussex County Solar + storage · Peter's Bridge Solar, LLC |
170 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)