United States βΊ Grid βΊ Interconnection queues βΊ Virginia
BATTERY STORAGE Β· PJMBattery storage project AG1-534, Loudoun County
Battery storage project AG1-534, Loudoun County is a 200 MW battery storage request withdrawn in the PJM interconnection queue, in Loudoun County, Virginia, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedSep 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-534
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Evergreen Mills 230 kV
- Location
- Loudoun County, Virginia
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 September 2020
- Proposed online date
- June 2023
- Withdrawn
- September 2023
Location
Marker shows the centre of Loudoun County; the queue data does not give exact sites.
Other requests in Loudoun County
- New Road StorageBattery storage Β· 120 MW Β· agreement signed
- Dulles Solar and BESSSolar Β· 100 MW Β· agreement signed
- Dulles Solar and BESSBattery storage Β· 50.0 MW Β· agreement signed
- Battery storage project AH1-727, Loudoun CountyBattery storage Β· 425 MW Β· in study
- Evergreen Energy CenterBattery storage Β· 20.0 MW Β· in study
- Stonewall Energy ParkGas Β· 800 MW Β· built
- Battery storage project AG2-287, Loudoun CountyBattery storage Β· 150 MW Β· withdrawn
- Battery storage project AG1-020, Loudoun CountyBattery storage Β· 150 MW Β· withdrawn
- Battery storage project AG2-285, Loudoun CountyBattery storage Β· 150 MW Β· withdrawn
- Battery storage project AG2-323, Loudoun CountyBattery storage Β· 100 MW Β· withdrawn
- Battery storage project AG2-325, Loudoun CountyBattery storage Β· 100 MW Β· withdrawn
- Battery storage project AH1-729, Loudoun CountyBattery storage Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem