πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Virginia

BATTERY STORAGE Β· PJM

Battery storage project AH1-444, City Of Chesapeake County

Battery storage project AH1-444, City Of Chesapeake County is a 200 MW battery storage request withdrawn in the PJM interconnection queue, in City Of Chesapeake County, Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedOct 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-444
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Fentress β€šΓ„Γ¬ Sligo 230 kV
Location
City Of Chesapeake County, Virginia
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
September 2025
Withdrawn
October 2021

Location

Marker shows the centre of City Of Chesapeake County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in City Of Chesapeake County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem