United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Indiana (2022 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7113.5 GW
Active in queue13.5 GW71 requests
Agreement signed50.0 MW1 requests
Withdrawn10416.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

71 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J2440, Benton County
Onshore wind
100 MWIn study Benton, INMISO Sep 2022target 2027
Solar + storage project AI1-081, Jay County
Solar + storage
100 MWIn study Jay, INPJM Jul 2022target 2026
Battery storage project J3166, Knox County
Battery storage
100 MWIn study Knox, INMISO Sep 2022target 2026
Battery storage project J2450, Tippecanoe County
Battery storage
100 MWIn study Tippecanoe, INMISO Sep 2022target 2026
Battery storage project AH2-233, Pulaski County
Battery storage
100 MWIn study Pulaski, INPJM Mar 2022target 2026
Solar project J1785, Laporte County
Solar
100 MWIn study Laporte, INMISO Jan 2022target 2024
Solar + storage project J2301, Vigo County
Solar + storage
100 MWIn study Vigo, INMISO Mar 2022target 2025
Solar + storage project AI1-009, Rush County
Solar + storage
100 MWIn study Rush, INPJM Apr 2022target 2026
Solar project J2296, Sullivan County
Solar
100 MWIn study Sullivan, INMISO Mar 2022target 2025
Onshore wind project J2048, Benton County
Onshore wind
100 MWIn study Benton, INMISO Mar 2022target 2025
Battery storage project AH2-227, Jay County
Battery storage
75.0 MWIn study Jay, INPJM Mar 2022target 2026
Surplus; J1067
Other
60.0 MWIn study White, INMISO May 20222024
Surplus; J1369
Other
50.0 MWAgreement signed Dubois, INMISO May 2022target 2022
Solar project AH2-223, Jay County
Solar
50.0 MWIn study Jay, INPJM Mar 2022target 2025
Battery storage project J3140, Porter County
Battery storage
50.0 MWIn study Porter, INMISO Sep 2022target 2026
Battery storage project J2045, Newton County
Battery storage
50.0 MWIn study Newton, INMISO Mar 2022target 2024
Surplus; J1386
Other
50.0 MWIn study Lake, INMISO May 2022target 2028
Battery storage project AH2-371, Jay County
Battery storage
50.0 MWIn study Jay, INPJM Mar 2022target 2026
Battery storage project J1861, Laporte County
Battery storage
45.0 MWIn study Laporte, INMISO Mar 2022target 2024
Solar project J3208, Dubois County
Solar
10.0 MWIn study Dubois, INMISO Sep 2022target 2023
Surplus; Petersburg
Other
3.0 MWIn study Pike, INMISO May 2022target 2023
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)