United States › Grid › Interconnection queues › Indiana

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Indiana — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6911.2 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

69 requests · page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1391, Dubois County
Solar
100 MWAgreement signed Dubois, INMISO Apr 2019target 2025
Tillman Solar Park
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Sun Chief Solar Farm
Solar
100 MWAgreement signed Jay, INPJM Jul 2020target 2027
Solar project J1369, Dubois County
Solar
100 MWAgreement signed Dubois, INMISO Apr 2019target 2025
Solar project J1392, Lagrange County
Solar
100 MWAgreement signed Lagrange, INMISO Apr 2019target 2025
Hawthorn Solar
Solar
83.0 MWAgreement signed Delaware, INPJM Sep 2019target 2028
Fall Creek Energy Storage
Battery storage
80.0 MWAgreement signed Madison, INPJM Mar 2020target 2028
BR Solar Sheriff 1
Solar
75.0 MWAgreement signed Grant, INPJM Sep 2020target 2028
Solar project J1387, Jasper County
Solar
60.0 MWAgreement signed Jasper, INMISO Apr 2019target 2024
Surplus; J1369
Other
50.0 MWAgreement signed Dubois, INMISO May 2022target 2022
Flatrock Creek Storage I
Battery storage
50.0 MWAgreement signed Allen, INPJM Sep 2020target 2029
Trade Post Energy Storage
Battery storage
50.0 MWAgreement signed Sullivan, INPJM Mar 2019target 2028
Solar project J1235, Knox County
Solar
50.0 MWAgreement signed Knox, INMISO Apr 2019target 2023
Lake Trout Solar
Solar
45.0 MWAgreement signed Blackford, INPJM Mar 2020target 2028
New Jay PV & BESS
Solar + storage
39.0 MWAgreement signed Jay, INPJM Sep 2020target 2028
Maple Solar
Solar
35.0 MWAgreement signed Huntington, INPJM Mar 2019target 2028
Onshore wind project J1470, Benton County
Onshore wind
30.0 MWAgreement signed Benton, INMISO Apr 20192020
Battery storage project J1323, Lagrange County
Battery storage
25.0 MWAgreement signed Lagrange, INMISO Apr 2019target 2025
Bitter Ridge Wind Farm
Onshore wind
12.6 MWAgreement signed Jay, INPJM May 2020target 2025
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)