Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown529112.4 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

529 requests · page 2 of 11
ProjectCapacityStatusLocationRegionQueuedOnline
APC Barry 8 CC
Gas
685 MWOperating Mobile, ALSoutheast 2023
West Georgia Gen. Co.(Block 1)
Gas
680 MWOperating Southeast 2000
TA Smith (+50 MW)
Gas
664 MWOperating Whitfield, GASoutheast 2018
Other project 62, Whitfield County
Other
640 MWOperating Whitfield, GASoutheast Sep 1999
Other project 55
Other
640 MWOperating Southeast Aug 1999
Duke-Sandersville CT
Gas
640 MWOperating Southeast 2002
Other project 55, Marshall County
Other
640 MWOperating Marshall, KYSoutheast Aug 1999
Other project 62
Other
640 MWOperating Southeast Sep 1999
Gas project 135, Polk County
Gas · Osprey Combined Cycle
637 MWOperating Polk, FLSoutheast Nov 20142004
Harris 2 (Autauga 2)
Gas
630 MWOperating Southeast 2003
Harris 1 (Autauga 1)
Gas
630 MWOperating Southeast 2003
Gas project 210, Haywood County
Gas
630 MWOperating Haywood, TNSoutheast Jun 2007
Calhoun Power Company I (Kinetics)
Gas
628 MWOperating Southeast 2003
Franklin 2 (Goat Rock 2)
Gas
620 MWOperating Southeast 2003
Thomas A Smith (Conasauga)
Gas
620 MWOperating Southeast 2002
Coal project 17, Berkeley County
Coal · SCPSA
620 MWOperating Berkeley, SCSoutheast Apr 2001target 2005
Franklin 3 (Goat Rock 3)
Gas
620 MWOperating Lee, ALSoutheast 2017
Other project 40, Weakley County
Other
600 MWOperating Weakley, TNSoutheast Feb 1999
Coal project 23, Berkeley County
Coal · SCPSA
600 MWOperating Berkeley, SCSoutheast Jan 2005target 2006
Other project 40
Other
600 MWOperating Southeast Feb 1999
Coal project 24, Berkeley County
Coal · SCPSA
600 MWOperating Berkeley, SCSoutheast Jan 2005target 2009
Kemper County IGCC
Gas
592 MWOperating Kemper, MSSoutheast 2014
Franklin 1 (Goat Rock 1)
Gas
590 MWOperating Southeast 2002
Gas project 1
Gas · Duke Energy Florida, LLC
567 MWOperating Southeast Apr 1997
Gas project 1, Polk County
Gas · Duke Energy Florida, LLC
567 MWOperating Polk, FLSoutheast Apr 19971999
Gas project 10230
Gas · Duke Energy Carolinas LLC - Lincoln County CT
550 MWOperating Southeast Mar 20172020
BC Smith
Gas
547 MWOperating Effingham, GASoutheast Sep 20232024
Effingham (aka McCall Road)
Gas
540 MWOperating Effingham, GASoutheast Dec 2023
Coal project 16, Berkeley County
Coal · SCPSA
540 MWOperating Berkeley, SCSoutheast Apr 2001target 2005
Effingham Power (Blandford)
Gas
537 MWOperating Southeast 2003
Sewell Creek
Gas
518 MWOperating Polk, GASoutheast Dec 2023
Plant McDonough, Units 4A & 5A
Gas
506 MWOperating Cobb, GASoutheast 2023
Gas project 17114
Gas · NTE Carolinas, LLC
500 MWOperating Southeast Dec 20132018
Walton Bainbridge (aka E. Bainbr)
Gas
500 MWOperating Decatur, GASoutheast Dec 2023
Baconton
Gas
500 MWOperating Mitchell, GASoutheast Dec 2023
Plant McDonough, Units 4A & 5A
Gas
487 MWOperating Cobb, GASoutheast 2017
Gas project 5, Pasco County
Gas · Seminole Electric Cooperative, Inc.
480 MWOperating Pasco, FLSoutheast Oct 19992002
Other project , Choctaw County
Other
480 MWOperating Choctaw, MSSoutheast Dec 1997
Other project
Other
480 MWOperating Southeast Dec 1997
LGE Washington (aka Tiger Creek)
Gas
480 MWOperating Washington, GASoutheast Dec 2023
Other project 14, Haywood County
Other
460 MWOperating Haywood, TNSoutheast Jul 1998
Other project 14
Other
460 MWOperating Southeast Jul 1998
Other project 15, Lowndes County
Other
450 MWOperating Lowndes, MSSoutheast Jul 1998
Other project 15
Other
450 MWOperating Southeast Jul 1998
Talbot County
Gas
440 MWOperating Southeast Dec 2023
Gas project 33, Pinellas County
Gas · Duke Energy Florida, LLC
418 MWOperating Pinellas, FLSoutheast Mar 20062009
Battery storage project 371, Manatee County
Battery storage · FPL
409 MWOperating Manatee, FLSoutheast Oct 20192021
Other project 17
Other
390 MWOperating Southeast Jul 1998
Other project 17, Union County
Other
390 MWOperating Union, MSSoutheast Jul 1998
Hartwell Energy
Gas
354 MWOperating Hart, GASoutheast Dec 2023
Page 2 of 11

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)