Other project 40 is a 600 MW other request built and operating in the Southeast interconnection queue, connecting to Tennessee Valley Authority.
Request details
- Queue ID
- 40
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Technology
- Other: 600 MW
- Total requested
- 600 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 22 February 1999
Location
Marker shows the centre of County; the queue data does not give exact sites.
Other requests in County
- Other project 40, Weakley CountyOther Β· 600 MW Β· built
- Other project 116, Weakley CountyOther Β· 555 MW Β· withdrawn
- Gas project 209, Weakley CountyGas Β· 500 MW Β· withdrawn
- Other project 112, Weakley CountyOther Β· 280 MW Β· withdrawn
- Battery storage project 615, Weakley CountyBattery storage Β· 150 MW Β· withdrawn
- Solar project 528, Weakley CountySolar Β· 120 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem