LGE Washington (aka Tiger Creek)

LGE Washington (aka Tiger Creek) is a 480 MW gas request built and operating in the Southeast interconnection queue, in Washington County, Georgia, connecting to Georgia Transmission.

Queue statusOperating
  1. PlanningQueued Dec 2023 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GI-016
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Georgia Transmission
Connection point (POI)
Tiger Creek 230 kV Sub
Location
Washington County, Georgia
Technology
Gas: 480 MW
Total requested
480 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
31 December 2023

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.