GAS · SOUTHEASTFranklin 3 (Goat Rock 3)
Franklin 3 (Goat Rock 3) is a 620 MW gas request built and operating in the Southeast interconnection queue, in Lee County, Alabama, connecting to Southern Company.
Request details
- Queue ID
- IC-214
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Location
- Lee County, Alabama
- Technology
- Gas: 620 MW
- Total requested
- 620 MW
- Study phase
- Operational
- Queue status
- Operational
- Agreement signed
- 7 August 2006
- Came online
- June 2017
Location
Marker shows the centre of Lee County; the queue data does not give exact sites.
Other requests in Lee County
- Gas project 25-IC-1320A, Lee CountyGas · 240 MW · in study
- Gas project 25-IC-1321, Lee CountyGas · 111 MW · in study
- Solar project IC-1251, Lee CountySolar · 157 MW · suspended
- Solar + storage project IC-1052, Lee CountySolar + storage · 80.0 MW · suspended
- Franklin 2 (Goat Rock 2)Gas · 620 MW · built
- Franklin 1 (Goat Rock 1)Gas · 590 MW · built
- Gas project IC-252, Lee CountyGas · 968 MW · withdrawn
- Gas project IC-224, Lee CountyGas · 667 MW · withdrawn
- Gas project IC-203, Lee CountyGas · 655 MW · withdrawn
- Gas project IC-1218, Lee CountyGas · 640 MW · withdrawn
- Gas project IC-210, Lee CountyGas · 630 MW · withdrawn
- Gas project IC-104, Lee CountyGas · 630 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem