BC Smith

BC Smith is a 547 MW gas request built and operating in the Southeast interconnection queue, in Effingham County, Georgia, connecting to Southern Company.

Queue statusOperating
  1. PlanningQueued Sep 2023 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
IC-1177
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Location
Effingham County, Georgia
Technology
Gas: 547 MW
Total requested
547 MW
Study phase
Operational
Queue status
Operational
Entered queue
27 September 2023
Proposed online date
March 2024
Came online
June 2024

Location

Marker shows the centre of Effingham County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Effingham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem