United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2024 requests) — page 17

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,313251.4 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,313 requests · page 17 of 27
ProjectCapacityStatusLocationRegionQueuedOnline
Halo Energy Storage
Battery storage · MN8 Energy Development Company LLC
100 MWWithdrawn / abandoned Wyoming, NYNYISO Aug 2024
Solar project J3684, Morgan County
Solar
100 MWWithdrawn / abandoned Morgan, ILMISO Apr 2024target 2028
Solar project IC-1270, Floyd County
Solar
100 MWWithdrawn / abandoned Floyd, GASoutheast Mar 2024
Solar project J3244, Parke County
Solar
100 MWWithdrawn / abandoned Parke, INMISO Mar 2024target 2028
Solar project J3578, Greene County
Solar
100 MWWithdrawn / abandoned Greene, ARMISO Apr 2024target 2027
File Cabinet Storage
Battery storage · Kerhonkson, LLC
100 MWWithdrawn / abandoned Ulster, NYNYISO Sep 2024
Zenobe Stockton LLC
Battery storage · Zenobe Stockton LLC
100 MWWithdrawn / abandoned Chautauqua, NYNYISO Sep 2024
Glove City Solar
Solar · Glove City Energy Center, LLC
100 MWWithdrawn / abandoned Montgomery, NYNYISO Oct 2024
Solar project J3772, Panola County
Solar
100 MWWithdrawn / abandoned Panola, MSMISO Apr 2024target 2028
Moffitt ESC
Battery storage · Fresh Air Energy II, LLC
100 MWWithdrawn / abandoned Suffolk, NYNYISO Oct 2024
Zenobe Lancaster LLC
Battery storage · Zenobe Lancaster LLC
100 MWWithdrawn / abandoned Erie, NYNYISO Sep 2024
Blue Mountain BESS
Battery storage · ACE DevCo NC, LLC
100 MWWithdrawn / abandoned Ulster, NYNYISO Sep 2024
Solar project 664, Chickasaw County
Solar
100 MWWithdrawn / abandoned Chickasaw, MSSoutheast Oct 2024
Solar project 617, Caldwell County
Solar
100 MWWithdrawn / abandoned Caldwell, ALSoutheast Jun 2024
Harrigan Solar
Solar · ACE DevCo NC,LLC
100 MWWithdrawn / abandoned Franklin, NYNYISO Sep 2024
Winterberry Wind
Onshore wind · Winterberry Wind LLC
100 MWWithdrawn / abandoned Bradford, PANYISO Sep 2024
Solar project J3514, Chippewa County
Solar
100 MWWithdrawn / abandoned Chippewa, MIMISO Apr 2024target 2028
Battery storage project C4-078, Salt Lake County
Battery storage
100 MWWithdrawn / abandoned Salt Lake, UTWest May 2024target 2027
Battery storage project J3284, Woodford County
Battery storage
100 MWWithdrawn / abandoned Woodford, ILMISO Apr 2024target 2028
Battery storage project J3290, White County
Battery storage
100 MWWithdrawn / abandoned White, INMISO Apr 2024target 2028
Lewis Wind
Onshore wind · Lewis Wind, LLC
100 MWWithdrawn / abandoned Lewis, NYNYISO Oct 2024
Battery storage project J3813, Putnam County
Battery storage
100 MWWithdrawn / abandoned Putnam, INMISO Apr 2024target 2028
Birch-Whistler
Onshore wind · Birch Whistler, LLC
100 MWWithdrawn / abandoned Delaware, NYNYISO Sep 2024
Amsterdam Energy Storage
Battery storage · BGTF US Development Holdings LLC
100 MWWithdrawn / abandoned Montgomery, NYNYISO Sep 2024
Janes Rd Storage
Battery storage · MN8 Energy Operating Company
100 MWWithdrawn / abandoned Monroe, NYNYISO Jan 2024
Solar project J3793, Rapides Parish County
Solar
100 MWWithdrawn / abandoned Rapides Parish, LAMISO Apr 2024target 2028
Warrior Storage
Battery storage · Springville BESS, LLC
100 MWWithdrawn / abandoned Erie, NYNYISO Sep 2024
Solar project J3668, Cheboygan County
Solar
100 MWWithdrawn / abandoned Cheboygan, MIMISO Apr 2024target 2028
Battery storage project J3339, Hendricks County
Battery storage
100 MWWithdrawn / abandoned Hendricks, INMISO Apr 2024target 2028
Battery storage project IC-1268, Fulton County
Battery storage
100 MWWithdrawn / abandoned Fulton, GASoutheast Mar 2024
Battery storage project J3804, Putnam County
Battery storage
100 MWWithdrawn / abandoned Putnam, INMISO Apr 2024target 2028
Battery storage project J3372, Macoupin County
Battery storage
100 MWWithdrawn / abandoned Macoupin, ILMISO Apr 2024target 2028
Middletown Energy Storage
Battery storage · Middletown Energy Storage LLC
100 MWWithdrawn / abandoned Orange, NYNYISO Oct 2024
Battery storage project 143, King County
Battery storage
100 MWWithdrawn / abandoned King, WAWest Apr 2024target 2027
Battery storage project C4-080, Multnomah County
Battery storage
100 MWWithdrawn / abandoned Multnomah, ORWest May 2024target 2027
Solar project PIS078, Power County
Solar · PacifiCorp
100 MWWithdrawn / abandoned Power, IDWest Jun 2024target 2029
Solar project GEN-2024-006, Lawrence County
Solar
100 MWWithdrawn / abandoned Lawrence, ARSPP Apr 2024target 2029
Jefferson Energy Storage
Battery storage · Jefferson Energy Storage
100 MWWithdrawn / abandoned Lewis, NYNYISO Sep 2024
Zenobe Wellsville LLC
Battery storage · Zenobe Americas Inc.
100 MWWithdrawn / abandoned Allegany, NYNYISO Sep 2024
Vidal Blanc Storage
Battery storage · Vidal Blanc Storage 1, LLC
100 MWWithdrawn / abandoned Ulster, NYNYISO Sep 2024
Solar project J3675, Greene County
Solar
100 MWWithdrawn / abandoned Greene, ARMISO Apr 2024target 2029
Seventy Seven Project
Solar · Good Ole 77 Energy LLC
100 MWWithdrawn / abandoned Wyoming, NYNYISO Aug 2024
Battery storage project J3757, Dubuque County
Battery storage
100 MWWithdrawn / abandoned Dubuque, IAMISO Apr 2024target 2028
Lincoln ESC
Battery storage · Fresh Air Energy II, LLC
100 MWWithdrawn / abandoned Suffolk, NYNYISO Oct 2024
Solar project 653, Lake County
Solar
100 MWWithdrawn / abandoned Lake, TNSoutheast Sep 2024
Solar project J3868, Sharp County
Solar
100 MWWithdrawn / abandoned Sharp, ARMISO Dec 2024target 2029
Zenobe Harmony LLC
Battery storage · Zenobe Harmony LLC
100 MWWithdrawn / abandoned Chautauqua, NYNYISO Sep 2024
Solar + storage project C4-084, Duchesne County
Solar + storage
100 MWWithdrawn / abandoned Duchesne, UTWest May 2024target 2029
Battery storage project J3807, Goodhue County
Battery storage
100 MWWithdrawn / abandoned Goodhue, MNMISO Apr 2024target 2028
Battery storage project J3816, Saginaw County
Battery storage
100 MWWithdrawn / abandoned Saginaw, MIMISO Apr 2024target 2028
Page 17 of 27

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)