United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2016 requests) — page 13

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,194150.9 GW
Active in queue25.8 GW162 requests
Agreement signed18.1 GW106 requests
Withdrawn1,194150.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,194 requests · page 13 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 150, Hardee County
Solar · Masked
74.9 MWWithdrawn / abandoned Hardee, FLSoutheast Jun 2016target 2019
Solar project IC-560, Pike County
Solar
74.9 MWWithdrawn / abandoned Pike, GASoutheast Dec 2016
Solar project 138B, Bradford County
Solar · Masked
74.9 MWWithdrawn / abandoned Bradford, FLSoutheast Apr 2016target 2019
Solar project 138A, Hamilton County
Solar · Masked
74.9 MWWithdrawn / abandoned Hamilton, FLSoutheast Apr 2016target 2019
Solar project 138C, Highlands County
Solar · Masked
74.9 MWWithdrawn / abandoned Highlands, FLSoutheast Apr 2016target 2019
Solar project IC-558, Jackson County
Solar
74.9 MWWithdrawn / abandoned Jackson, FLSoutheast Dec 2016
Solar project 153, Columbia County
Solar · Penholoway Solar, LLC
74.9 MWWithdrawn / abandoned Columbia, FLSoutheast Jul 2016target 2019
Solar project 139, Gilcrhist County
Solar · Masked
74.9 MWWithdrawn / abandoned Gilcrhist, FLSoutheast Apr 2016target 2018
Solar project 159, Hamilton County
Solar · Duke Energy Florida, LLC
74.9 MWWithdrawn / abandoned Hamilton, FLSoutheast Sep 2016target 2020
Solar project 146, Polk County
Solar · Masked
74.8 MWWithdrawn / abandoned Polk, FLSoutheast May 2016target 2020
Solar project 145, Polk County
Solar · Masked
74.8 MWWithdrawn / abandoned Polk, FLSoutheast May 2016target 2020
Solar project 165, Osceola County
Solar · Florida Renewable Partners, LLC
74.5 MWWithdrawn / abandoned Osceola, FLSoutheast Dec 2016target 2021
Solar project 17
Solar
74.5 MWWithdrawn / abandoned FLSoutheast May 2016target 2019
Solar project 167, Hamilton County
Solar · Masked
74.5 MWWithdrawn / abandoned Hamilton, FLSoutheast Dec 2016target 2018
Solar project 166, Hamilton County
Solar · Florida Renewable Partners, LLC
74.5 MWWithdrawn / abandoned Hamilton, FLSoutheast Dec 2016target 2021
Solar project 192, Manatee County
Solar · FPL
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast May 2016target 2027
Solar project 170, Columbia County
Solar · Masked
74.5 MWWithdrawn / abandoned Columbia, FLSoutheast Dec 2016target 2018
Solar project 66052, Chester County
Solar
74.5 MWWithdrawn / abandoned Chester, SCSoutheast Apr 2016
Solar project IC-482, Jackson County
Solar
74.5 MWWithdrawn / abandoned Jackson, FLSoutheast Aug 2016
Onshore wind project GEN-2016-002, Swisher County
Onshore wind
74.0 MWWithdrawn / abandoned Swisher, TXSPP Mar 2016target 2018
Solar project J634, Calcasieu Parish County
Solar
72.0 MWWithdrawn / abandoned Calcasieu Parish, LAMISO May 2016target 2020
Wild West Solar
Solar
71.6 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2020
Solar project IC-563, Macon County
Solar
71.4 MWWithdrawn / abandoned Macon, GASoutheast Dec 2016
Yermo Solar 1
Solar
71.1 MWWithdrawn / abandoned San Bernardino, CACAISO May 2016target 2019
Solar project IC-557, Coffee County
Solar
70.4 MWWithdrawn / abandoned Coffee, GASoutheast Dec 2016
Solar project 5703, Montgomery County
Solar
70.2 MWWithdrawn / abandoned Montgomery, NCSoutheast Jun 2016
Solar project 10586, Caswell County
Solar
70.1 MWWithdrawn / abandoned Caswell, NCSoutheast Sep 2016
Solar project GEN-2016-093, Scotts Bluff County
Solar
70.0 MWWithdrawn / abandoned Scotts Bluff, NESPP Oct 2016target 2018
Onshore wind project G0553, Hood River County
Onshore wind
70.0 MWWithdrawn / abandoned Hood River, ORWest Aug 2016target 2019
Solar project Company HB, Pershing County
Solar
70.0 MWWithdrawn / abandoned Pershing, NVWest Mar 2016target 2024
Solar project 746, Crook County
Solar
70.0 MWWithdrawn / abandoned Crook, ORWest May 2016target 2018
Onshore wind project J615, Black Hawk County
Onshore wind
70.0 MWWithdrawn / abandoned Black Hawk, IAMISO May 2016target 2018
Solar project J581, Morehouse Parish County
Solar
70.0 MWWithdrawn / abandoned Morehouse Parish, LAMISO May 2016target 2020
Solar project AC1-211, Fulton County
Solar
70.0 MWWithdrawn / abandoned Fulton, PAPJM Oct 2016target 2018
Solar project IC-493, Dale County
Solar
70.0 MWWithdrawn / abandoned Dale, ALSoutheast Sep 2016
Solar project IC-502, Dodge County
Solar
68.5 MWWithdrawn / abandoned Dodge, GASoutheast Sep 2016
Solar project IC-512, Wilcox County
Solar
68.5 MWWithdrawn / abandoned Wilcox, GASoutheast Oct 2016
Solar project IC-483, Tift County
Solar
68.4 MWWithdrawn / abandoned Tift, GASoutheast Aug 2016
Combined Cycle GT
Gas
68.0 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2016target 2020
Waymart Wind II
Onshore wind
67.3 MWWithdrawn / abandoned Wayne, PAPJM Sep 2016target 2021
Desert Obsidian
Solar
67.2 MWWithdrawn / abandoned Clark, NVCAISO May 2016target 2020
Solar project 288, Colbert County
Solar
67.0 MWWithdrawn / abandoned Colbert, ALSoutheast Mar 2016
Solar project 294, Haywood County
Solar
67.0 MWWithdrawn / abandoned Haywood, TNSoutheast Jun 2016
Solar project 289, Jackson County
Solar
67.0 MWWithdrawn / abandoned Jackson, ALSoutheast Mar 2016
Solar project 726, Crook County
Solar
66.0 MWWithdrawn / abandoned Crook, ORWest Jan 2016target 2018
Solar project 281, Benton County
Solar
66.0 MWWithdrawn / abandoned Benton, TNSoutheast Feb 2016
Solar project 277, Lowndes County
Solar
65.0 MWWithdrawn / abandoned Lowndes, MSSoutheast Jan 2016
Solar
Solar
65.0 MWWithdrawn / abandoned Cheshire, NHISO-NE Apr 2016target 2018
Gas project AB2-154, Kendall County
Gas
65.0 MWWithdrawn / abandoned Kendall, ILPJM Apr 2016target 2017
ESC Brooke County Power I, LLC
Gas
65.0 MWWithdrawn / abandoned Brooke, WVPJM Apr 2016target 2021
Page 13 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)