United States βΊ Grid βΊ Interconnection queues βΊ North Carolina
SOLAR Β· SOUTHEASTSolar project 10586, Caswell County
Solar project 10586, Caswell County is a 70.1 MW solar request withdrawn in the Southeast interconnection queue, in Caswell County, North Carolina, connecting to Duke Energy Progress.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2016 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 10586
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Progress
- Connection point (POI)
- Marion-Whiteville 230kV
- Location
- Caswell County, North Carolina
- Technology
- Solar: 70.1 MW
- Total requested
- 70.1 MW
- Service type
- Other
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 21 September 2016
Location
Marker shows the centre of Caswell County; the queue data does not give exact sites.
Power plants in North Carolina Β· Transmission lines in North Carolina
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem