United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

SOLAR Β· MISO

Solar project J581, Morehouse Parish County

Solar project J581, Morehouse Parish County is a 70.0 MW solar request withdrawn in the MISO interconnection queue, in Morehouse Parish County, Louisiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedMay 2021 (project stopped here)
  3. ConsentedMay 2018 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J581
Grid region
MISO (Midcontinent)
Connection point (POI)
Bastrop - Sterlington 115kV Line
Location
Morehouse Parish County, Louisiana
Technology
Solar: 70.0 MW
Total requested
70.0 MW
Study phase
GIA
Queue status
Withdrawn
Entered queue
9 May 2016
Agreement signed
2 May 2018
Proposed online date
October 2020
Withdrawn
May 2021

Location

Marker shows the centre of Morehouse Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Morehouse Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem