United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA — page 124

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 124 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Lager Storage
Battery storage · Momentum Lager LLC
31.1 MWIn study Nueces, TXERCOT Feb 2022target 2028
Gas project GEN-2024-018, Gage County
Gas
31.0 MWIn study Gage, NESPP Oct 2024target 2030
Geothermal project 25-00425, Pershing County
Geothermal
31.0 MWIn study Pershing, NVWest Jul 2025target 2030
Hidden Knolls BESS
Battery storage
30.8 MWIn study Kern, CACAISO Apr 2021target 2028
Hooper Storage
Solar + storage · BT Brown Solar, LLC
30.7 MWIn study Lee, TXERCOT Dec 2022target 2027
Gas project AH1-706, Trumbull County
Gas · Clean Energy Future - Lordstown, LLC
30.5 MWIn study Trumbull, OHPJM Apr 2025
Solar project AI2-145, Montgomery County
Solar
30.4 MWIn study Montgomery, VAPJM Feb 2023target 2022
M-Bar Solar I
Solar + storage · M-Bar Energy I, LLC
30.2 MWIn study Ector, TXERCOT Dec 2024target 2028
Half Moon Battery
Battery storage
30.2 MWPaused / redesign Hidalgo, TXERCOT Sep 2018
Solar + storage project AH2-409, Wood County
Solar + storage
30.1 MWIn study Wood, OHPJM Mar 2022target 2025
Solar project AI2-337, Madison County
Solar
30.0 MWIn study Madison, OHPJM Mar 2023target 2023
Battery storage project AH2-031, Jefferson County
Battery storage
30.0 MWIn study Jefferson, WVPJM Nov 2021target 2025
Gas project 956475, Anderson County
Gas
30.0 MWIn study Anderson, SCSoutheast Jun 2024
Battery storage project AI2-278, Lancaster County
Battery storage
30.0 MWIn study Lancaster, VAPJM Mar 2023target 2027
Solar + storage project 556, Grant County
Solar + storage · Prairie City PV1, LLC
30.0 MWPaused / redesign Grant, ORWest Apr 2019target 2024
Solar + storage project AG2-191, Grant County
Solar + storage · BR Solar Sheriff 2 LLC
30.0 MWIn study Grant, INPJM Feb 2025target 2023
Gas project Q66, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Nov 2020target 2022
Redbud-Gaylord 34.5 kV
Solar
30.0 MWPaused / redesign Frederick, VAPJM Jul 2020target 2026
Gas project Q81, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Jun 2021target 2025
Battery storage project G0733, Benton County
Battery storage
30.0 MWIn study Benton, WAWest Mar 2022target 2025
Battery storage project AI2-311, Washington County
Battery storage
30.0 MWIn study Washington, MDPJM Mar 2023target 2025
Spinel Solar
Solar
30.0 MWPaused / redesign Medina, TXERCOT Aug 2017
Black Diamond Solar
Battery storage · Black Diamond Solar Power, LLC
30.0 MWIn study Christian, ILPJM Sep 2020target 2022
Solar project 957086, Darlington County
Solar
30.0 MWIn study Darlington, SCSoutheast Jun 2024
Battery storage project AI2-227, Amherst County
Battery storage
30.0 MWIn study Amherst, VAPJM Mar 2023target 2023
Gas project 12-048, Morrow County
Gas
30.0 MWPaused / redesign Morrow, ORWest Feb 2012target 2012
Solar + storage project AH2-411
Solar + storage
30.0 MWIn study KYPJM Mar 2022target 2025
Coal project 978035, Forsyth County
Coal
30.0 MWIn study Forsyth, NCSoutheast May 2025
Battery storage project AH2-059, Prince William County
Battery storage
30.0 MWIn study Prince William, VAPJM Dec 2021target 2027
Coal project 978034, Forsyth County
Coal
30.0 MWIn study Forsyth, NCSoutheast May 2025
Surplus; J903
Other
30.0 MWIn study MISO Oct 2020
Gas project Q65, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Nov 2020target 2022
Other project PP00054, Darlington County
Other
30.0 MWIn study Darlington, SCSoutheast Oct 2025target 2027
Solar project AH2-117, Pike County
Solar
30.0 MWIn study Pike, KYPJM Feb 2022target 2026
Solar project AG2-081, Montgomery County
Solar · SR Fayette II, LLC
30.0 MWIn study Montgomery, KYPJM Mar 2025target 2024
Solar project J2908, Morgan County
Solar
30.0 MWIn study Morgan, ILMISO Jul 20222023
Battery storage project AH2-058, Prince William County
Battery storage
30.0 MWIn study Prince William, VAPJM Dec 2021target 2026
Onshore wind project PIS052, Carbon County
Onshore wind · PacifiCorp
30.0 MWIn study Carbon, WYWest Feb 2024target 2024
Battery storage project AG2-566, Prince Edward County
Battery storage · Gabriel Storage, LLC
30.0 MWIn study Prince Edward, VAPJM Feb 2025target 2024
Solar project AH2-057, Buckingham County
Solar
29.9 MWIn study Buckingham, VAPJM Dec 2021target 2025
Hoffman Falls Wind 2
Onshore wind · Liberty Renewables Inc.
29.8 MWIn study Madison, NYNYISO Aug 2024target 2027
Solar project 287, Fairfield County
Solar
29.7 MWIn study Fairfield, SCSoutheast May 2025target 2027
Solar project AI2-471, Montour County
Solar
29.5 MWIn study Montour, PAPJM Mar 2023target 2025
Solar project AI2-338, Charles City County
Solar
29.2 MWIn study Charles City, VAPJM Mar 2023target 2024
Battery storage project AH2-075, City Of Hampton County
Battery storage
29.1 MWIn study City Of Hampton, VAPJM Jan 2022target 2024
Solar project AI2-473, Montour County
Solar
29.0 MWIn study Montour, PAPJM Mar 2023target 2026
Gas project G005, Lincoln County
Gas
29.0 MWIn study Lincoln, MNMISO Feb 1999target 2004
Geothermal project IA-PNM-2014-04, Dona Ana Cty County
Geothermal
29.0 MWIn study Dona Ana Cty, NMWest Mar 2014target 2018
Solar project AI1-119, Kendall County
Solar
28.8 MWIn study Kendall, ILPJM Sep 2022target 2026
Solar project AI2-152, Madison County
Solar
28.8 MWIn study Madison, INPJM Mar 2023target 2025
Page 124 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)