United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2015 requests) โ€” page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown80095.6 GW
Active in queue15.8 GW73 requests
Agreement signed8,536 MW38 requests
Withdrawn80095.6 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

800 requests ยท page 11 of 16
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-417, Dallas County
Solar
19.7 MWWithdrawn / abandoned Dallas, ALSoutheast Aug 2015
Solar project IC-402, Berrien County
Solar
19.7 MWWithdrawn / abandoned Berrien, GASoutheast Jan 2015
Solar project IC-418, Greene County
Solar
19.7 MWWithdrawn / abandoned Greene, ALSoutheast Aug 2015
Solar project IC-409, Long County
Solar
19.7 MWWithdrawn / abandoned Long, GASoutheast Feb 2015
Solar project IC-414, Houston County
Solar
19.7 MWWithdrawn / abandoned Houston, ALSoutheast Jun 2015
Sharon Solar
Solar ยท Sharon Solar LLC
19.6 MWWithdrawn / abandoned Schoharie, NYNYISO May 2015
Yaphank Fuel Cell Park
Battery storage ยท Yaphank Fuel Cell Park, LLC
19.6 MWWithdrawn / abandoned Suffolk, NYNYISO Mar 2015
EPCAL Fuel Cell Park
Battery storage ยท EPCAL Fuel Cell Park, LLC
19.6 MWWithdrawn / abandoned Suffolk, NYNYISO Mar 2015
Setauket Fuel Cell Park
Battery storage ยท Setauket Fuel Cell Park, LLC
19.6 MWWithdrawn / abandoned Suffolk, NYNYISO Mar 2015
Onshore wind project J454, Lyon County
Onshore wind
18.9 MWWithdrawn / abandoned Lyon, MNMISO May 2015target 2016
Mason Dixon Solar Center Facility
Solar
18.4 MWWithdrawn / abandoned Washington, MDPJM Oct 2015target 2018
Lincoln Park
Other ยท Lincoln Park DG LLC
18.3 MWWithdrawn / abandoned Dutchess, NYNYISO May 2015
Saugerties
Other ยท NY DG Holding LLC
18.3 MWWithdrawn / abandoned Dutchess, NYNYISO May 2015
East Kingston
Other ยท East Kingstson DG LLC
18.3 MWWithdrawn / abandoned Dutchess, NYNYISO May 2015
North Catskill
Other ยท North Catskill DG LLC
18.2 MWWithdrawn / abandoned Greene, NYNYISO Jul 2015
Blue Circle
Battery storage ยท Blue Circle DG LLC
18.2 MWWithdrawn / abandoned Greene, NYNYISO Jul 2015
Bridgeport Energy Wet Compression Upgrade
Gas
18.0 MWWithdrawn / abandoned Fairfield, CTISO-NE Feb 2015target 2018
Solar project Q231, Cochise County
Solar
17.5 MWWithdrawn / abandoned Cochise, AZWest Oct 2015target 2016
wind
Onshore wind
17.4 MWWithdrawn / abandoned Franklin, VTISO-NE Feb 2015target 2016
Gas project AB1-117, Fluvanna County
Gas
17.3 MWWithdrawn / abandoned Fluvanna, VAPJM Oct 2015target 2016
Battery storage project AA2-064, Sussex County
Battery storage
17.0 MWWithdrawn / abandoned Sussex, NJPJM Feb 2015target 2015
Solar project J507, Pulaski County
Solar
16.7 MWWithdrawn / abandoned Pulaski, ARMISO Nov 2015target 2016
Solar project AB1-162, Queen Anne's County
Solar
16.7 MWWithdrawn / abandoned Queen Anne's, MDPJM Oct 2015target 2017
Battery storage project AA2-117, Sussex County
Battery storage
16.0 MWWithdrawn / abandoned Sussex, NJPJM Apr 2015target 2016
Solar project IC-420, Liberty County
Solar
16.0 MWWithdrawn / abandoned Liberty, GASoutheast Nov 2015
Solar project AA2-113, Halifax County
Solar
16.0 MWWithdrawn / abandoned Halifax, NCPJM Apr 2015target 2017
Route 632 Washington Solar Facility
Solar
16.0 MWWithdrawn / abandoned Washington, MDPJM Apr 2015target 2017
Solar project 507, Baker County
Solar
15.0 MWWithdrawn / abandoned Baker, ORWest Oct 2015
Stevensburg Solar
Solar
15.0 MWWithdrawn / abandoned VAPJM Oct 2015target 2019
Solar project AB1-129, Franklin County
Solar
15.0 MWWithdrawn / abandoned Franklin, PAPJM Oct 2015target 2017
Glens Falls Hydro
Hydro ยท Erie Boulevard Hydropower, LP
14.8 MWWithdrawn / abandoned Washington, NYNYISO Jul 2015
Solar project 275, Winston County
Solar
14.0 MWWithdrawn / abandoned Winston, MSSoutheast Nov 2015
Solar project AA2-036, Dorchester County
Solar
14.0 MWWithdrawn / abandoned Dorchester, MDPJM Jan 2015target 2015
Other project AA2-044, Cumberland County
Other
13.5 MWWithdrawn / abandoned Cumberland, NJPJM Feb 2015target 2016
Battery storage project AB1-114, Mercer County
Battery storage
12.5 MWWithdrawn / abandoned Mercer, PAPJM Oct 2015target 2017
Combustion Turbine
Gas
12.0 MWWithdrawn / abandoned Middlesex, MAISO-NE Feb 2015target 2016
Solar project 508, Baker County
Solar
12.0 MWWithdrawn / abandoned Baker, ORWest Oct 2015
Hydro project 656, Utah County
Hydro
11.5 MWWithdrawn / abandoned Utah, UTWest Apr 2015target 2018
Hydro project 645, Utah County
Hydro
11.5 MWWithdrawn / abandoned Utah, UTWest Feb 2015target 2017
Solar project 495, Baker County
Solar
11.0 MWWithdrawn / abandoned Baker, ORWest May 2015
CleanLight Power Solar Facility
Solar
10.9 MWWithdrawn / abandoned Garrett, MDPJM Aug 2015target 2019
Solar project 649, Washington County
Solar
10.3 MWWithdrawn / abandoned Washington, UTWest Mar 2015target 2016
Solar project 476, Malheur County
Solar
10.0 MWWithdrawn / abandoned Malheur, ORWest Mar 2015
Solar project 702, Jackson County
Solar
10.0 MWWithdrawn / abandoned Jackson, ORWest Aug 2015target 2016
Solar project 676, Wallowa County
Solar
10.0 MWWithdrawn / abandoned Wallowa, ORWest Jun 2015target 2016
Solar project 703, Klamath County
Solar
10.0 MWWithdrawn / abandoned Klamath, ORWest Aug 2015target 2016
Solar project AA2-085, Washington County
Solar
10.0 MWWithdrawn / abandoned Washington, MDPJM Mar 2015target 2016
Solar project 473, Malheur County
Solar
10.0 MWWithdrawn / abandoned Malheur, ORWest Mar 2015
Solar project AB1-158, Perry County
Solar
10.0 MWWithdrawn / abandoned Perry, OHPJM Oct 2015target 2017
Onshore wind project 653, Umatilla County
Onshore wind ยท Oregon Wind Farms, LLC
10.0 MWWithdrawn / abandoned Umatilla, ORWest Apr 2015target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)