SOLAR · PJMRoute 632 Washington Solar Facility
Route 632 Washington Solar Facility is a 16.0 MW solar request withdrawn in the PJM interconnection queue, in Washington County, Maryland, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2015 (completed)
- Withdrawn / abandonedJul 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AA2-159
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Downsville 34.5kV
- Location
- Washington County, Maryland
- Technology
- Solar: 16.0 MW
- Total requested
- 16.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Withdrawn
- Entered queue
- 30 April 2015
- Proposed online date
- September 2017
- Withdrawn
- July 2020
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
- East Hagerstown SolarSolar · 11.8 MW · agreement signed
- Battery storage project AI2-311, Washington CountyBattery storage · 30.0 MW · in study
- Lappans 34.5kV ProjectSolar · 20.0 MW · built
- Hagerstown PlantSolar · 10.0 MW · built
- Pinesburg Solar ProjectSolar · 4.3 MW · built
- Battery storage project AG1-470, Washington CountyBattery storage · 50.0 MW · withdrawn
- Solar project AG1-458, Washington CountySolar · 40.0 MW · withdrawn
- Solar project AF2-357, Washington CountySolar · 24.0 MW · withdrawn
- Solar project AG2-078, Washington CountySolar · 20.0 MW · withdrawn
- Solar project AG2-279, Washington CountySolar · 20.0 MW · withdrawn
- Mason Dixon Solar Center FacilitySolar · 18.4 MW · withdrawn
- Downsville SolarSolar · 16.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem