BATTERY STORAGE Β· NYISO

Blue Circle

Blue Circle is a 18.2 MW battery storage request withdrawn in the NYISO interconnection queue, in Greene County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2015 (completed)
  2. Withdrawn / abandonedFeb 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
508
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Blue Circle DG LLC
Connection point (POI)
LaFarge - PV 115 kV
Location
Greene County, New York
Technology
Other Storage: 18.2 MW
Total requested
18.2 MW
Queue status
Withdrawn
Entered queue
17 July 2015
Withdrawn
February 2016

Location

Marker shows the centre of Greene County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Greene County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem